HG 1/2018 · CLAUSE GUIDE

Annex 2 · Design and build

General information — not legal advice. Unofficial explanations and translation.

What the markings show

Gold highlighting identifies subclauses with official amendment notes, not individual inserted or deleted words. Blue notes explain related legislation and do not replace HG 1 wording. Switching off hides editorial markings; the consolidated text and official notes remain available.

Applicability, legislative updates and security

Start with the right contract

Annex 1 covers works execution; Annex 2 covers design and build. In the latter, design forms part of the programme, resourcing and Contractor responsibility. Procurement dates and transitional rules matter: reviewing an older contract does not mean automatically substituting the latest consolidated wording.

Legislative updates and contract applicability

The HG 1 annexes displayed on Portal Legislativ incorporate amendments through the 24 May 2024 consolidation. Later legislation can affect contract application without rewriting those annexes: CATUC, security rules and court jurisdiction must be read alongside the contractual model. The status of the acts and proposals below was checked on 12 November 2026.

  • CATUC transition: article 577 protects specified public investments governed by HG 907/2016 from Book II, Part IV (project stages). Relevant cases include works already under execution, certain procurements or documentation, and approved funding. This is a bounded exception, not exclusion from the whole Code. Article 582 separately addresses planning procedures already started and certificates already issued. The contract signature date alone does not decide applicability.

  • A changed design solution: check separately the permit and CATUC article 293, HG 1 clause 37’s contractual process, and the procurement modification basis in Law 98/2016 article 221 or Law 99/2016 article 235. Supervisor approval does not replace a permit or the procurement justification.

  • Design checking: the 14 October CATUC rectification directs article 277(1) to article 440 on technical design checking, rather than checking a BIM model. Contractual Supervisor approval and statutory professional checking are distinct functions. A statutory exception does not automatically remove an agreed contractual obligation.

  • Additional cost or time: clause 48.8 concerns legislative changes published after the Base Date that affect performance. Assess applicability, actual effect, notice and substantiation under clause 69a; costs already reflected in adjustment indices cannot be recovered twice. An error in the Contractor’s own design does not become a change in law.

  • Acts and proposals: the published rectification changes the Code’s text; MDLPA clarifications explain its application. Order 1389/2026 on certain balcony enclosures has its own limited scope and does not amend HG 1. Bill L638/2026 was in committee when checked on 12 November; it is not an obligation in force. The CATUC article separates these developments.

CATUC · art. 277, 293, 440, 577, 582 · MDLPA · L638/2026

CATUC: explanations and change history

Court jurisdiction · clause 70.6

Clause 70.6 still refers to the tribunal’s civil division. That historical wording does not by itself determine today’s competent court: Law 101/2016 article 53 and binding High Court Decision 11/2023 identify the administrative and fiscal division for the execution disputes concerned, filed from 10 September 2022. Check the claim’s subject and filing date, procedural law and any valid arbitration agreement. Do not assume court deadlines stop merely because amicable discussions have begun.

Legea 101/2016 · art. 53 · ÎCCJ 11/2023

Performance security: HG 1 and the separate legislation

Performance security secures fulfilment of the contract. It is distinct from clause 47 Retention Money and advance-payment security. The table separates an act’s effective date from the conditions for applying it to a project. Examples are fictional and assume the stated conditions are met.

What may be customised?

The Agreement supplies project parameters. Special Conditions may detail only the subclauses and subjects allowed by the Specific Conditions; the list does not permit unrestricted rewriting. Open the subclause to read it in context, then check the Specific Conditions text.

Specific Conditions and model Agreement →

CLAUSE GUIDE

Who decides, and which document prevails

1Definitions

The definitions govern the entire contract. Contract Price is the agreed price excluding VAT; Contract Value tracks payments made and estimated, including variations and adjustments. Time for Completion starts on the Commencement Date, while the Warranty Period starts when taking-over at completion is approved. Confusing those milestones leads to incorrect time, security or payment calculations.

The Base Date is normally 30 days before the tender submission deadline; where there was no such deadline, it is the signing date. The Baseline Programme is the programme accepted by the Supervisor, not simply a schedule submitted by the Contractor. Plant is incorporated into the Works; Contractor's Equipment is used to execute them. Clause headings do not form part of the legal provisions, and singular and plural are interpreted in context.

A shared vocabulary

A capitalised term may have a narrower meaning than in ordinary language. Distinguish Contract Price, Contract Value and Cost before making calculations.

Applying the clause

  • Contract reference sheet: parties, representatives, defined documents and dates.

2Contract language

Romanian is the language of the Contract and communications between the Contractor, Employer and Supervisor unless the Agreement provides otherwise. Their representatives are also covered: an international team does not automatically change the language required for a contractual notice.

A working translation helps the team understand the documents but does not change the language agreed in the Contract Agreement. For example, an internal report may be bilingual while the formal notice and relevant attachments are prepared in the contractual language.

Working language

Clause 2.1 defaults to Romanian for the contract and communications unless the Agreement states otherwise. A team translation does not change that rule.

Applying the clause

  • A version register: governing document, working translation and reviewer.

3Document precedence

The documents explain one another, but they do not have equal priority when they conflict. The Contract Agreement ranks first, followed by the Tender Form, Special Conditions and General Conditions. The technical-document order differs between Annex 1 and Annex 2 and is reproduced in full below.

An addendum takes the rank of the document it changes. A higher-ranking document prevails in a discrepancy; the Supervisor issues clarifications or instructions where wording is ambiguous. For example, two different completion periods are resolved by identifying the documents, versions and contractual ranking, rather than choosing the more convenient period.

Two documents specify different requirements

Illustrative example

The specification and technical tender state different performance requirements for the same installation.

  1. Identify the contract documents and revisions, then apply clause 3 of the applicable annex.
  2. Send the discrepancy to the Supervisor, identifying both requirements precisely. Request clarification where the documents are ambiguous.

The contract documents and issued clarification establish the solution to be built. The Contractor cannot simply choose the cheaper option.

The documents explain one another. If their provisions conflict, the document higher in the contractual order below prevails.

Applying the clause

  • Amendments and addenda have the priority of the documents they modify. The Supervisor issues the necessary clarification or instruction when documents are ambiguous.

Document order

  1. Contract Agreement
  2. Completed and, where applicable, corrected Tender Form
  3. Special Conditions
  4. General Conditions
  5. Employer’s Requirements
  6. Payment Schedule
  7. Contractor’s Tender and the other contractual documents listed in clause 3.1

4Communications

Contractual communications must identify the Contract name and number and reach the address stated in the Agreement through an allowed channel: post, fax, digitally signed email or personal delivery. A site discussion or informal message does not automatically replace a written notice required by another clause.

Where there is a receipt deadline, the sender requests acknowledgement and takes the steps needed for timely delivery. Contractor–Supervisor communications are copied to the Employer; Contractor–Employer communications are copied to the Supervisor. Consent, approval, certification and decisions must not be unreasonably withheld or delayed. Proof of receipt makes the applicable deadlines verifiable.

A notice with evidence of receipt

Illustrative example

Missing information may block a scheduled activity. Mentioning it at a meeting does not provide a complete record.

  1. Identify the contract, missing document and affected activity in writing, using the contractual address and communication channel.
  2. Request acknowledgement where receipt is subject to a deadline. Retain the notice, attachments and transmission evidence, and copy the Employer or Supervisor as clause 4 requires.

The record establishes what was communicated and when. A claim must also meet clause 69a requirements.

Communications identify the contract and use its nominated addresses. Request acknowledgement when receipt has a deadline; copy the Employer on correspondence with the Supervisor and vice versa.

Applying the clause

  • Correspondence register: recipient, copy, channel, deadline and receipt evidence.

5Supervisor

In Annex 2, the Supervisor also oversees design: reviewing and approving documents within its mandate, monitoring progress, quality, tests and payment certification, and issuing contractual orders and decisions. The Employer defines its duties and delegations to a representative must be communicated.

Approval does not transfer the Contractor’s design responsibility. A useful authority matrix distinguishes technical checking, contractual approval, variation instructions and matters requiring Employer consent. Record each order’s number, date, issuer and subject.

Who may issue an instruction

The Supervisor’s mandate and written delegations identify who may act. A designer’s site instruction is implemented after inclusion in the Supervisor’s Administrative Order.

Applying the clause

  • Authority matrix and Administrative Order register, recording number, date and issuer.

6Assignment

Assignment changes who holds a right or a part of the Contract; it is different from engaging a subcontractor to execute work. The general rule requires a written agreement and the other party's prior consent. The Contractor cannot freely transfer its obligations, and the Employer's approval does not release it from responsibility for work already performed or the unassigned part.

There are defined exceptions: either party may assign receivables to a bank as security with prior notice; direct payment to subcontractors who opted for it follows Clauses 50 and 52; following termination by the Employer, subcontracts may be transferred at its request. Replacement of the Contractor through reorganisation, merger or division is permitted only where the original qualification criteria are met, no other substantial modification occurs and procurement rules are not circumvented.

For example, securing a loan against contract receivables does not transfer the construction obligation to the bank. Transferring the whole execution obligation to another company is a different matter, governed by both the clause and procurement law. A noncompliant assignment can trigger breach and termination remedies.

Assignment needs its own record

Do not confuse assignment of the contract with subcontracting work. Identify the exact right or obligation transferred and the required consents.

Applying the clause

  • Written assignment, consents and obligations remaining with the assignor.

7Subcontracting

Subcontracting means entrusting part of the Contract to a third party through a written agreement. The subcontract must be compatible with the main contract and becomes an appendix to it; its prices may differ because costs and margins differ. The Contractor remains responsible for the acts, defaults and negligence of subcontractors at every tier, even after Employer approval.

Subcontractors declared in the tender are deemed accepted, and their subcontracts are submitted at signing. A new or replacement subcontractor proposed later requires a request identifying scope, value, identity, exclusion and capacity checks, and acceptance of the contract and technical tender. The Employer has 30 days to give a reasoned response; under the clause, silence by that deadline constitutes approval. The signed copy is sent within 5 days of approval, before work starts. Those periods must be coordinated with applicable statutory requirements, including documents due before commencement, and do not authorise a substantial modification.

Subcontractor or supplier? What the company actually performs and who organises the activity matter. Clause 7.1 excludes mere equipment hire, provision of labour and supply of goods. Article 3(1)(yy) of Law 98/2016 links subcontracting to performing and organising part of the works or services. Calling an agreement “services” is not enough to classify it.

Illustrative examples: hiring an excavator for operations managed by the Contractor differs from engaging a company to deliver an entire earthworks section under its own organisation and responsibility for the result. Buying steel is supply; delivering a reinforcement and installation package may be subcontracting. A designer taking on design included in Annex 2 performs part of the contract. A laboratory, surveyor or crane with an operator requires examination of actual scope, organisation and procurement documents; profession alone is not a reliable test.

Replacement also requires checking effects on qualification or tender scoring, rather than Employer consent alone. ANAP Instruction 1/2021 addresses limits on contract modification; Instruction 1/2017 clarifies certain cases involving access to specialists and authorisations. The clause requires monthly reporting of payments to subcontractors; unjustified delay may lead to suspension of payments to the Contractor. Direct payment has its own procedure under Clause 52 and the law; it does not itself determine how a company is classified.

Track subcontracting by scope

For each subcontractor, connect its work scope with approvals and the signed subcontract. Approval does not remove the Contractor’s responsibility for performance.

Applying the clause

  • Register: scope, firm, approval, subcontract, resources and mobilisation date.

Classification references: Law 98/2016 · articles 3 and 218–220; ANAP Instruction 1/2021; ANAP Instruction 1/2017. Examples are illustrative; classification depends on the actual work and procurement documents.

8Employer documents

Employer’s Requirements define the output: brief, mandatory characteristics, performance, standards, tests and operating/training documents. The feasibility study has its stated contractual role; it should not be treated as a fully warranted execution design supplied by the Employer.

After commencement, the Contractor examines requirements and reference data within the Agreement’s period, notifies errors and follows the contractual response. Distinguish mandatory requirements, information and the Contractor’s tendered solution. A late-discovered error is not automatically an Employer risk if diligent review could have found it.

An error in the Employer’s Requirements

Illustrative example

Initial review identifies a contradiction between required capacity and design information supplied by the Employer.

  1. Notify the Supervisor within the 8.4 period: 90 days from the Commencement Date by default, unless the Agreement sets another period.
  2. A report may organise errors, documents and estimated effects, but must satisfy the notice requirements. Also check whether diligent review could have identified the error before tender.

Notice does not automatically grant time or money. Apply 8.4–8.5 and, where entitlement exists, the claim procedure in 69a.

The document register should also show missing information, applicable revisions and required delivery dates. In design and build, track the Employer’s Requirements explicitly.

Applying the clause

  • Delivery and revision register, queries and the programme effect of late information.

9Site access

Site access is a dated obligation, not an implicit assumption. Special Conditions may divide handover by section and date; otherwise access and possession are due within 30 days of the Commencement Date. The Contractor must also allow others access as required by the Contract or Supervisor's instructions.

Land and facilities are used only for the Contract, maintained and restored before taking-over, allowing for normal wear. Delayed access may support a claim for time and Costs plus profit where the effects and procedural compliance are established. For example, handing over a section without access to the critical workfront should be reflected in the programme and handover records, rather than concealed by a general statement that “the site was handed over”.

Access as a programme milestone

Track promised and actual access by work area. An unavailable front may affect the sequence even when other areas are accessible.

Applying the clause

  • Area-by-area handover plan, records and documented restrictions.

10Permits and legal assistance

By default, the Employer is responsible for the urban-planning certificate, environmental instrument and approvals assigned to it. The Contractor prepares documents and takes the steps necessary for the Employer to obtain the permit for Permanent Works it designs, including associated approvals in the Employer’s name.

Temporary Works permits and other consents assigned to the Contractor remain its responsibility. No work proceeds without a valid permit. Record the holder, document author, applicant, due date, conditions and expiry so that “the Employer obtains the permit” does not conceal missing designer submissions.

Permits without ownership gaps

For each permit, identify the responsible party, required inputs and dependent activity. Check permitted project-specific provisions.

Applying the clause

  • Permit matrix: issuer, owner, submission, response and validity.

11Employer personnel

Employer's Personnel includes the Supervisor, its representatives and people employed and designated for that purpose by the Employer. Their powers come from delegation communicated in writing to the Contractor, effective on receipt. Withdrawal of delegation must also be communicated in writing.

A person's presence on site does not itself confer authority to change works or approve costs. The team should be able to identify who may request information, inspect, certify or instruct, within the delegation and the Supervisor's contractual role.

Cooperation on site

Integrate the Employer’s personnel and other participants into site coordination. Record coordination problems with a location and an observable effect.

Applying the clause

  • Interface owners, access arrangements and coordination minutes.

CLAUSE GUIDE

Organising delivery

12General obligations

Under Annex 2 the Contractor designs, executes, completes and remedies the Works. Its design must meet the purpose defined in the Employer’s Requirements and/or the contractual design brief; this includes work needed for strength, stability and operational safety even if not expressly listed. The Contractor provides the resources and is responsible for operations and methods. A reasoned objection to an Administrative Order exceeding authority or Contract scope is due within 10 days and does not suspend the Order; the Supervisor responds within 10 days, with silence constituting confirmation.

The clause also sets administrative discipline: information requested by the Employer is supplied within 5 days; records are retained as required by law and for at least 10 years after final payment; the Employer may inspect, copy and audit them. Confidentiality continues for 10 years after final payment, subject to stated exceptions, including using the Contract as a tendering or marketing reference.

Joint venture members are individually and jointly and severally liable; the leader and composition cannot change without prior consent. Third-party support is a concrete undertaking to provide resources or actions, which may be called upon when the Contractor fails in the supported obligations. Standards are tied to the Base Date; later introduction of new standards follows the variation mechanism and statutory limits, rather than an informal change to the tender. For new technical regulations relevant to the design of the Permanent Works, Annex 2 applies this mechanism to adoption and publication after the building permit is issued.

Turn general duties into assigned work

Execution and remedying defects require people, materials, plant and documents. Translate contractual duties into assigned work and evidence of completion.

Applying the clause

  • Obligations register: requirement, owner, due date and completion evidence.

12aCode of conduct

The code of conduct prohibits using contractual authority for private gain, offering or receiving benefits that influence performance, and activities incompatible with contractual duties. Public statements about the Contract require the Employer's prior approval, and the Contractor cannot bind the Employer without consent.

The clause also covers unusual commercial expenses: commissions without real and legitimate services, unidentified beneficiaries, shell companies and other listed situations. The Employer and oversight bodies may examine documents and operations. Legitimate judicial or out-of-court settlements between the parties are not prohibited; the distinction is between a documented settlement and a benefit offered to influence conduct.

Make conduct part of site management

People working on the contract need to understand and apply the conduct requirements. Document induction and incidents rather than relying on declarations alone.

Applying the clause

  • Induction records, a reporting owner and records of action taken.

12bConflicts of interest

A conflict of interest may arise from a shared financial, economic or personal interest between decision-makers in the Contractor, joint venture or subcontractors and those in the Employer or Supervisor. A biased decision need not already have occurred: the duty is to prevent or remove a situation that could compromise objective performance.

The Contractor notifies the Employer without delay and immediately takes measures; the Employer may assess them and require more. Decision-making personnel exposed to such a situation must be replaced immediately at no cost to the Employer. A record of declarations, measures and changes of role helps demonstrate how the conflict was addressed.

Identify conflicts early

Assess and manage a potential conflict before it affects contractual decisions. Retain the notification and mitigation trail.

Applying the clause

  • Declarations, a situation register and measures separating responsibilities.

13Management of the works

The Contractor's Representative is empowered to make decisions for performance, receive and implement orders and sign submitted documents. If not named in the Contract, the nomination is due within 15 days of signing and the Supervisor responds within 10 days. The Representative's time is devoted entirely to coordinating the Contract; the Contractor ensures effective communication in the contractual language.

Management also includes an internal quality assurance system, authorised personnel, procedures and conformity documents submitted before each execution stage. The Supervisor may audit the system, but compliance does not remove the Contractor's responsibility. Environmental protection measures are required on and off site, including compliance with emission, discharge and waste limits. The management record should therefore connect decision-makers with the procedures and evidence actually used during execution.

The representative who can act

Identify the Contractor’s representative, authority and deputy. The team must know who receives instructions and sends the contractual response.

Applying the clause

  • Appointment, authority, contact details and replacement procedure.

14Personnel

Staffing must be sufficient for the current programme and appropriately skilled. The proposed Representative and key personnel are maintained throughout the Works, except for justified replacements allowed by the clause. The Supervisor may require removal with reasons for serious or repeated breaches or conduct jeopardising occupational safety or the environment.

Replacing key personnel requires the Employer's prior consent and evidence of qualifications and experience at least equivalent to the requirements. If the individual contributed tender evaluation points, the replacement must achieve at least the same score. For example, a CV meeting the minimum qualification threshold may still be insufficient to replace an expert who earned the maximum award score.

Proposed staff and mobilised staff

Match actual people, competence and availability with the tender and contract requirements. Track replacements through the applicable procedure.

Applying the clause

  • Organisation chart, qualifications, acceptances, availability and replacement history.

15Performance security

Performance Security secures performance of the Contract. The Agreement sets its amount; without one, the General Conditions default to 10% of the Price. The clause requires provision within 5 working days and permits a guarantee instrument or successive deductions where the procurement documents and parties allow them. The deduction route requires an account at the Employer’s disposal and an initial deposit of at least 0.5%.

Track validity through final acceptance and adjust the amount when the Price changes. Calls are tied to specified events and notice identifying the breached obligations and calculation. By default, 70% is released within 14 days after taking-over approval, subject to the clause, and the balance at final acceptance. Keep performance security, retention money and advance repayment security separate in the financial register.

The current statutory framework and special replacement regime are explained in the “Performance security” section. Read the clause alongside them, including Law 77/2026 approving OUG 3/2024.

Security: separate legislation and examples

Checking security amount and validity

Illustrative example

A fictional contract price is EUR 1,000,000 excluding VAT and the Agreement sets security at 10%.

  1. The initial amount to check is EUR 100,000. Compare it with the issued instrument or accepted constitution mechanism.
  2. Check the beneficiary, calling conditions, expiry and extension duties separately. A change in price or duration may require adjustments.

A correct amount does not cure an expired instrument. Assess release against the applicable contractual and statutory milestones described in the security table.

Record the performance-security amount separately from any deductions used to build it and from retention money. Read the Agreement and relevant clauses for each mechanism.

Applying the clause

  • The consolidated text requires provision within 5 working days of signing and defaults to 10% if the Agreement supplies no amount. Read these periods together with overriding legislation applicable to the procurement.
  • Track validity through final acceptance, extension of the instrument and adjustment after a price change. Under 15.6, the Agreement’s percentage (70% by default) is released within 14 days of taking over, subject to its conditions; the balance follows final acceptance.

16Responsibilities and insurance

The clause separates responsibility for the Works, damage to the Employer and third-party claims. The Contractor generally bears responsibility for integrity of the Works until taking-over and remains liable for obligations continuing afterwards. Monetary limits have exceptions, including fraud, gross negligence and certain bodily injuries; they are not a general release from liability.

Insurance must remain effective, not merely appear on a checklist: works, third parties, vehicles, occupational accidents and quality liability. Supply policies and certificates, monitor premiums and expiry, and replace an insurer where required. The Supervisor’s receipt of documents does not transfer the risk. For example, a policy expiring during an extension leaves the Contractor’s contractual obligations in place.

Risk and insurance are different questions

A policy does not automatically cover every contractual liability. Compare allocated risks with insured parties, limits, deductibles, exclusions and cover periods.

Applying the clause

  • Insurance matrix and expiry calendar, including evidence that premiums are paid.

17Programme

The design-and-build Programme includes investigations, design stages, checks and approvals, consents and permits, then procurement, construction, tests and acceptance. Design resources—disciplines, checkers, instruments and software—are shown separately from construction resources.

The editable Gantt and narrative follow the deadlines, critical-path, update and acceptance rules in the text. Before technical design is complete, execution detail is adapted; afterwards activities and resources are fully detailed. The narrative describes design stages and methods, teams, S-curves and cash flow. Acceptance of a longer schedule does not automatically extend contractual time.

A programme must explain dependencies

Illustrative example

Installation is scheduled before the team receives the necessary documents and completes procurement.

  1. Link document preparation, checking, approval, purchasing and installation through real dependencies, with assigned resources and responsibilities.
  2. Show actual progress, departures from the Reference Programme and proposed measures. Annex 2 also requires explicit tracking of the Contractor’s design stages.

The programme supports assessment of a delay. Moving every bar to a later date neither explains its cause nor grants a contractual extension.

Prepare two coordinated documents. The schedule shows when and in what sequence work proceeds; the narrative explains why that sequence is achievable. Updates compare both documents with the Baseline Programme.

Applying the clause

Gantt schedule · 17.2

  • Include investigations, design stages, checking and approval, together with design resources. Adapt construction detail until the technical design is complete, then fully detail it.
  • Phases, structures, work categories, locations and subcontractors; activities broken down to no more than 30 calendar days.
  • Resources, quantities, costs and productivities allocated to activities; durations stated in days.
  • Start-to-start, finish-to-start or finish-to-finish links; a visible critical path. One activity without a predecessor and one without a successor, subject to the clause’s justified exceptions.

Narrative report · 17.3

  • Description of design stages and the corresponding methods.
  • Construction method and how resources for critical activities will be secured.
  • Number and composition of crews; workforce allocated by month.
  • Plant types, numbers, capacities and periods of use; subcontractors and their resources.
  • Physical and financial progress S-curves, together with the cash-flow forecast.

Submission and updates · 17.1, 17.4–17.12

  • Initial submission: within 30 days of the Commencement Date, on paper and in editable electronic format. The Supervisor reviews within 15 days; no response within that period means deemed acceptance.
  • Following rejection: resubmit within 10 days. The accepted initial programme becomes the Baseline Programme; payments other than an advance depend on its acceptance.
  • Monthly: within the first 10 days, submit the updated Gantt and narrative, differences from the baseline, causes and recovery measures. The Supervisor’s review period is 5 days.
  • Revise when events affect critical activities or timely completion is no longer achievable. Acceptance of a revised schedule does not itself grant a contractual extension.

18Price breakdown

In Annex 2, the breakdown is due within 30 days after technical-design approval: proposed unit prices for design quantities, identifying labour, materials, equipment, transport, overheads and profit.

It does not convert the lump-sum contract into a remeasurement contract. The Supervisor may use it to assess variation impact or value parts without being bound by the proposal. Link it to the Schedule of Payments and the design revision producing the quantities.

A price that can be traced

The breakdown explains the price and supports valuation. Link its components to the accepted tender and the selected annex’s payment mechanism.

Applying the clause

  • Traceable breakdown: quantities, resources, costs and mapping to contract items.

19Design responsibilities

The Contractor designs Permanent and Temporary Works, fulfils the statutory designer’s role and is responsible for the solution, checking and required technical assistance. Design must meet the Employer’s Requirements and technical Tender; correction of its own errors is not automatically a payable Variation.

The clause covers the whole chain: accepted designers, submission and approval, permits, corrections, taking-over documents, as-built records and manuals. Supervisor approval does not transfer responsibility. Track each deliverable’s revision, checker, status and approval date and integrate the Agreement’s design and permitting periods into the programme.

Design through to construction documents

Illustrative example

The Contractor develops the installation design against the Employer’s Requirements.

  1. Connect deliverables to mandatory requirements, responsible designers, statutory checking and contractual approval.
  2. Resolve comments and revisions before using documents for the relevant activities, and track final handover documents.

Supervisor approval does not remove the Contractor’s design responsibility. Correcting its own error is not automatically an Employer-funded Variation.

Annex 2: the Contractor designs the works against Employer Requirements; track verification, approval and final documents.

Applying the clause

  • The Contractor designs the Permanent and Temporary Works. Link each deliverable to the Employer’s Requirements, design checking and required approvals.
  • The design register should identify disciplines, authors, checkers, revisions, comments and documents for construction and handover.

20Adequacy of the contract price

The Contractor interprets Site data and bases its Tender on its own calculations and diligent examination. In Annex 2, the Price and payment schedule cover design and execution obligations, including those without a separately allocated sum.

Estimating quantities for its own solution is ordinarily its risk, not automatic remeasurement. Distinguish mandatory Employer requirements, the tendered solution and physical unknowns potentially covered by clause 21. A tender-assumptions register helps establish that boundary.

The assumptions behind the tender

Pricing assumes examination of relevant information and risks before tendering. Retain the assumptions to distinguish an estimating error from a compensable event.

Applying the clause

  • Tender record: available data, inspection, assumptions, calculations and clarified exclusions.

21Exceptional risks

This clause concerns adverse physical conditions a diligent contractor could not reasonably foresee at tender: for example unknown utilities, unexploded ordnance or pollutants. Weather is excluded. Notify promptly on becoming aware, describing the conditions, effects and proposed measures.

The Supervisor may request estimates, approve measures or instruct a response; within 30 days it decides foreseeability and assesses whether a nonsubstantial variation is needed. Extra time and cost do not follow automatically from discovery: demonstrate and claim them under 69a. Dated photographs, investigations, locations and critical-path effects turn an assertion into an assessable claim.

When encountered conditions exceed the assumption

Describe the condition encountered and compare it with available information. Document the connection between event, response and impact before assessing entitlement.

Applying the clause

  • Notice, photographs, investigations, measures, resources and critical-path effect.

22Site safety

The Contractor controls access while permitting authorised persons and contractual access for neighbours or users. It protects personnel, third parties, existing structures and the Works from Site handover through taking-over and during warranty interventions.

Submit the Contractor’s health and safety plan within 30 days of commencement; it must be accepted before work starts. Appoint a safety officer with real authority to intervene. Imminent danger requires urgent action and notification; accidents and incidents must be reported and investigated under the Law. Supervisor acceptance of the plan does not transfer the Contractor’s responsibility.

Safety in everyday work

Link safety measures to activity risks and the people exposed. Checking implementation matters as much as having a plan.

Applying the clause

  • Plans, inductions, inspections and closure of corrective actions.

23Adjacent property

The Contractor protects neighbouring property and the public by designing and executing necessary measures and temporary works at its own cost and responsibility. The obligation extends to all areas in which it operates.

In design and build, assess the Contractor’s solution and neighbourhood effects during design. Link initial condition surveys, structural checks, monitoring and complaints records to the method and preventive measures.

Neighbouring property before and after work

An initial condition record helps distinguish existing damage from damage arising during work. Plan protection for affected properties.

Applying the clause

  • Condition surveys, dated photographs, protective measures and complaints register.

24Traffic and access routes

The Works must not obstruct traffic or communication routes beyond the limits permitted by the Contract. Route and vehicle selection must respect weight and dimensional restrictions. The Contractor repairs access damage caused by improper use.

Temporary or special access, strengthening and additional facilities are generally its responsibility; notify the Supervisor before implementing special measures. Transporting heavy equipment may require a bridge assessment and an alternative route, not merely booking a truck.

Traffic is a construction constraint

Coordinate work stages, local access and deliveries. Check restrictions and project-specific requirements before selecting the construction method.

Applying the clause

  • Traffic plans, approvals, work windows and user information.

25Utilities

Utilities identified in the Contract or discovered during design or construction must be preserved, protected, relocated or replaced under the Contract, Law and operator requirements. Investigation and coordination begin during design.

Where an activity affects service, immediately notify the Supervisor and take timely measures. Clauses 20 and 21 remain relevant to risk and entitlement; discovering a utility does not alone determine every cost. Retain operator confirmations and approved solutions for each interface.

Existing services

Read utility plans, field checks and utility-owner coordination together. An unexpected service requires a documented notification and resolution trail.

Applying the clause

  • Verified service map, owner correspondence, protection and approved diversions.

26Setting out

The Contractor is responsible for setting-out, positions, levels, dimensions and alignment and provides the necessary instruments and personnel. Supervisor checks do not release that responsibility. Protect survey benchmarks and markers throughout the Works.

Correct the Contractor’s own errors without extra time or payment. Where an error originates in contractual or Supervisor-supplied reference data and a diligent contractor could not detect it, time and cost relief may be claimed. Records of reference-network checks are essential to distinguish the two situations.

Reliable setting-out control

Control points and setting-out checks support the geometry of the whole work. Identify discrepancies early and retain checking measurements.

Applying the clause

  • Control-point handover, checked instruments, calculations and setting-out records.

27Site operations

Activities are confined to the Site and accepted ancillary areas. The Contractor removes rubble, waste, surplus materials and redundant temporary works, then leaves accepted areas clean and safe. Goods needed for warranty obligations may remain during that period.

The Contract allocates responsibility for demolition or excavation materials and transport/storage costs. Materials reserved to the Employer must be preserved and handed over rather than automatically treated as waste. Record quantities, destinations and handover evidence before removal.

Site organisation that supports delivery

Storage, movement and housekeeping form part of site organisation. Coordinate temporary occupation with activities and release of work fronts.

Applying the clause

  • Site layout, storage zones and records of material removal.

28Discoveries

Notify archaeological finds, rare objects or objects of scientific interest immediately to the Supervisor. Between the Parties, they remain the Employer’s property and responsibility; contractual classification is decided by the Employer subject to the Law.

Follow instructions for protecting and handling the discovery. If those instructions cause delay or cost, pursue entitlement under 69a with evidence linking the instruction, affected area and actual effect. A discovery does not automatically justify stopping the whole project where other workfronts can continue.

A discovery changes the work sequence

Relevant discoveries require protection and notification. Continuing work in the affected area is not simply a productivity decision.

Applying the clause

  • Location, photographs, notices, instructions and affected period.

29Temporary works

The Contractor provides Temporary Works and, unless otherwise specified, land, design, approvals, permits, construction, removal and reinstatement. Include these activities in price, resources and programme.

Where the documents prescribe particular Temporary Works and specify their location, that land is treated as part of the Site. This does not automatically reproduce Annex 1’s Employer-design exception. Check the actual responsibilities in the Employer’s Requirements.

The works that enable the permanent works

Supports, platforms and other temporary works have their own design, safety and removal requirements. Track them separately from the permanent works.

Applying the clause

  • Temporary-works register, designs, checks and permission to use.

30Plant and transport

Equipment must match the accepted Programme and have at least the quality and capacity offered and contracted. An equipment list without availability during critical periods does not satisfy mobilisation requirements.

The Contractor manages packing, loading, transport, receipt, unloading, storage and protection of Goods. Transport loss or expense does not create an entitlement to extra time or payment under this clause. Link delivery planning to the programme and access conditions.

Logistics before mobilisation

Plant capacity and delivery routes must suit work fronts and access restrictions. Plan exceptional transport before placing orders.

Applying the clause

  • Mobilisation plan, routes, permits and access-capacity checks.

31Overlapping contracts

The Contractor provides the conditions required by the Contract and instructions for other contractors or authorities to operate on or near the Site. These may include access, temporary works and, temporarily and exceptionally, equipment.

If this support was not provided for and the instruction causes extra time or cost, a claim may be available. Maintain an interface matrix and the actual instructions. Problems under one contract do not automatically permit delayed performance of another, nor can the Employer delay another contract’s payments on that basis.

Interfaces between contracts

A realistic programme includes dependencies on other contractors. Record handovers, shared access and activities that cannot proceed independently.

Applying the clause

  • Interface matrix, owners and minutes with actions and dates.

32Intellectual property

Rights created by the Contractor generally remain its property, but the Employer receives an irrevocable, royalty-free, non-exclusive licence for the Contract and use, maintenance and repair of the Works, including sublicensing and transfer. Employer documents may be used by the Contractor to perform the Contract.

The Contractor protects the Employer against third-party infringement claims, subject to the clause’s exceptions for imposed designs or instructions. Check licences for designs, software and third-party solutions: delivery of a file alone does not establish long-term rights to use and maintain it.

The right to use

Designs, technology and software must be lawfully usable. Check licences and responsibilities for third-party claims.

Applying the clause

  • Licences, permissions, rights holders and handover conditions for the Employer.

CLAUSE GUIDE

Time, change and delay

33Commencement

Annex 2 has separate design and execution commencement orders. The first is issued within 15 days of signing. The execution order follows completion of detailed design and obtaining permits, and sets commencement no later than 30 days after transmission; it may cover Sections.

Separate designer mobilisation, submissions, checking, permits and Site mobilisation in the programme. Starting design does not automatically authorise physical works. Retain orders and dates as contractual milestones, not merely calendar events.

The date that starts the clock

Connect the commencement instruction with mobilisation conditions and deadlines running from the Commencement Date. Signing and commencement are different events.

Applying the clause

  • Instruction, delivery evidence and the calendar of initial obligations.

34Time for completion

The period covers completion of all Works and each separately timed Section, including completion tests and obligations necessary for taking-over. The last physical activity is not necessarily the date on which the Contract allows the Works to be considered complete.

Plan backwards from taking-over: tests, quality records, the construction technical record, remedial work and notices. A schedule reaching the deadline with physical work alone while leaving tests until later may conceal contractual delay.

What to track

Take the Time for Completion and any sectional deadlines from the Agreement. Record the event that starts the clock alongside the commencement instruction.

Applying the clause

  • Track the warranty/defects period separately. An extension needs the basis in clause 35 and the applicable claim procedure.

35Extension of time

An extension requires a contractual cause and an effect on completion: exceptionally adverse weather as precisely defined, unforeseeable authority delay, orders not attributable to the Contractor, Employer default, qualifying suspension, force majeure or another express entitlement. The Contractor must mitigate delay.

Preserve entitlement through 69a or, where specified, a 69c.5 notice of disagreement. Programmes, diaries and critical-path analysis must connect the event to the days claimed. Time is extended by the Supervisor’s Decision, subject to review; acceptance of a late schedule alone is insufficient.

Activity delay versus completion delay

Illustrative example

Access is made available seven days later than scheduled.

  1. Identify affected activities, dependencies and the effect on completion using the relevant programme and daily records.
  2. Document reasonable mitigation and follow the contractual notice and substantiation process.

Seven days of late access do not automatically mean seven days of extension. The effect that gives rise to contractual entitlement must be demonstrated.

An extension needs a link between the contractual cause and affected activities. The programme and contemporaneous records should explain the effect on completion.

Applying the clause

  • Notice, chronology, programme analysis, mitigation and claim particulars.

36Delay

Progress meetings track issues and actions, but minutes do not amend the Contract. If progress is inadequate through the Contractor’s fault, it updates the programme within 10 days of notice and includes recovery measures, including additional resources.

The clause separates withholding for a missed milestone from penalties for late completion. Withholding is released when the milestone is achieved; daily delay penalties follow the Agreement and contractual cap. Check accepted Sections and the Employer’s claim procedure. Reaching the cap may permit termination, but expiry of the completion period does not automatically end the Contract.

The consequences of late completion

Track the applicable completion date, approved extensions and delay period. Read the daily amount and cap from the project contract.

Applying the clause

  • Separate calculations by section or milestone, with contractual basis and periods used.

37Variations

In design and build, changes to the Contractor’s own design or correction of errors are not Variations where they do not change the Employer’s Requirements or tendered solution. Quantity differences from its own estimate are generally Contractor risks.

An approved Variation identifies effects on requirements/design/works, programme, time, value and payment schedule. Contractor optimisation proposals have their own rules, including the cost of preparation and approvals. Do not execute a change requiring a new permit before obtaining it.

A different solution before construction

Illustrative example

A different item of equipment or technical solution is proposed against the contract documents.

  1. Identify the affected requirement, reason, cost difference and programme effect. Check permits and the procurement-law modification basis separately.
  2. Follow the approval route in clause 37. A technical discussion or quotation does not replace the required contractual instrument.

Under Annex 2, correcting the Contractor’s own design is not automatically a payable Variation. Establish cause and responsibility first.

Retain the instruction, changed scope, valuation and programme effect. Check the required approvals and procedure before executing the change.

Applying the clause

  • The contractual variation procedure does not replace the limits imposed by public procurement legislation.

38Suspension

Suspension may be ordered with its cause, responsible Party and duration or resumption conditions stated. The Contractor protects the Works while stopped. There is also a route for failure to certify or pay, subject to thresholds and prior notice; a late invoice alone does not permit immediate stoppage.

Time and financial consequences depend on the cause and allocated risk. Record personnel, equipment, protection and remobilisation actually required. Prolonged non-attributable suspension opens a resumption-request and possible termination procedure; track the separate 180-, 30- and 210-day periods without treating them as an automatic time extension.

Suspension is not abandonment

Stopping work requires protection, records and preparation for resumption. Separate the suspension instruction from its time and cost consequences.

Applying the clause

  • Instruction, inventory, preservation measures, resources and resumption instruction.

CLAUSE GUIDE

Evidence of quality

39Site diary

The Site Diary is the daily factual record: weather, hours, personnel, materials, equipment, tests, work, obstructions, incidents and orders. The Contractor’s Representative signs entries; the Supervisor checks and countersigns within 5 days. Without timely checking, the clause treats them as correct.

If the Supervisor records disagreement, the Contractor has 10 days for written comments; silence accepts that position. Record verifiable facts, locations and quantities and link photographs and tests to the entry. The diary supports progress and impact evidence but does not replace a claim notice.

The site diary as project memory

Useful entries record facts: what was done, where, by whom and under what conditions. Later conclusions rely on this daily evidence.

Applying the clause

  • Activities, quantities, resources, weather, instructions and events, linked to supporting records.

40Materials and equipment

Materials and permanent Plant must comply with the Contract and be procured in time for checking. Before use, the Contractor submits quality records, certifications and test results for the Supervisor’s consent. Samples identify their source and intended location.

Initial approval does not prevent later rejection if defects emerge. Separate proposed, documented, checked, accepted-for-use and incorporated states in the register. Taxes and royalties for off-site materials and their transport/storage are the Contractor’s responsibility.

Product approval before incorporation

Illustrative example

A supplier proposes a product serving the same purpose but with different characteristics from those specified.

  1. Compare conformity documentation and relevant characteristics with the contract requirements before ordering or incorporation.
  2. Establish whether this is a compliant product, a nonconformity or a change requiring approval; retain the response and batch identification.

A sales brochure alone neither establishes compliance nor authorises a changed solution.

Link materials and equipment to the technical requirement, approval and delivered batch. Sample acceptance does not replace delivery traceability.

Applying the clause

  • Technical sheets, declarations, certificates, samples, approvals and batch register.

41Inspection and testing

Quality control occurs at factories, storage locations and on Site, not only at taking-over. The Contractor supplies access, personnel, samples and testing facilities and convenes responsible parties at statutory hold points. Notify the Supervisor before covering work; failure may require uncovering at the Contractor’s cost.

Submit results and track the confirmation certificate, for which the clause provides 5 days and a consequence for silence. Additional tests confirming compliance may create recoverable costs subject to the claims procedure. Confirmation does not extinguish quality liability; retain traceability between sample, batch and work location.

Inspections within the programme

Plan tests and inspections before work is covered or proceeds. Coordinate notices, access and results with the activities.

Applying the clause

  • Inspection and test plan, hold points, notices and reports.

42Rejection

Noncompliant Materials or Plant are marked, removed and replaced; work incorporating them may be rejected. Rejected items and work are neither certified nor paid. The Supervisor may require demolition, reconstruction or repair despite earlier tests or payments.

The Contractor remedies promptly at its own cost and repeats testing. If it fails to comply, the Employer may engage others and recover costs through the contractual route. A nonconformity register should identify the defect, action, owner, deadline and closure evidence, not merely a photograph of the problem.

Follow nonconformity through closure

Rejection of material or work should lead to a defined action and verification of the result. Record the effect on dependent activities.

Applying the clause

  • Nonconformity record, instruction, remedy or replacement and reinspection.

43Ownership of materials

Goods brought for the Works are dedicated to the Contract and cannot be removed without acceptance. Following the declaration that Materials and Plant are free of encumbrances, they become the Employer’s property, while preservation, storage and loss risk remain with the Contractor until the relevant taking-over.

Ownership, custody and payment entitlement are separate milestones. Termination rules cover delivery of Employer-owned Goods and use of temporary works/equipment necessary for safety. Hire agreements must accommodate the specified mechanism for continued use by the Employer.

Ownership, risk and payment

Transfer of title, risk of loss and entitlement to payment have separate rules. Track them for delivered goods not yet incorporated.

Applying the clause

  • Inventory, identification, ownership evidence, insurance and payment-certificate link.

CLAUSE GUIDE

Following the money

44Payment principles

The default currency is the leu unless the Special Conditions provide otherwise; accounts and beneficial owners must be clear. No payment is made without valid Performance Security. Treasury accounts are required in the stated circumstances.

Amounts due to the Employer are established by agreement, decision or the applicable legal mechanism and deducted or paid within the contractual period. Precautionary payment suspension is also possible where termination conditions exist, limited to 60 days if termination does not follow. Financial checks must track these conditions as well as the invoice.

The foundations of payment

Identify the currency and general rules before building cash flow. Track project-specific provisions in the applicable contract document.

Applying the clause

  • Commercial reference sheet: currency, accounts and clauses governing valuation and payment.

45Contract value

Value starts from the lump-sum Price, except Provisional Sums, plus VAT and contractual adjustments or revisions. Where particular parts are paid by actual quantities or work, the Special Conditions must identify them and their measurement rules.

Separate the lump-sum result, provisional allowances, variations and adjustment in the forecast. The Supervisor warns of a predicted Price overrun and the Employer takes the required formal action; a new design bill of quantities does not itself increase the Contract.

From price to payable value

Do not track the signing price and value resulting from contract administration in one undifferentiated figure. Changes and valuations must reconcile.

Applying the clause

  • Register of price, addenda, variations and cumulative certified value.

46Advance payment

The Agreement determines whether advances exist and which mechanism applies. Under Annex 2’s 46.7 route, the default is two instalments: 5% of Price plus VAT at the start and 10% plus VAT after the Permanent Works permit, unless the Agreement specifies otherwise within statutory limits.

Each instalment requires its corresponding security and is justified through applicable deductions. Do not apply these percentages to a project whose Agreement excludes advances or uses the annual route. Track instalment, security, justification and balance separately.

Advance payment: is it allowed, and how is it recovered?

Start with the Agreement’s YES/NO choice and project parameters. A general clause describing advance payments does not establish that this project grants one.

Applying the clause

  • If the Agreement excludes advances, this clause does not apply. If allowed, payment requires valid Performance Security and an advance repayment guarantee and cannot precede the Commencement Date.
  • Under 46.6, read instalments and dates from the Agreement; the mechanism recovers advances through full deductions before actual payments. The alternative in 46.7 applies only where the Agreement allows justification by the contractual deadline.
  • For 46.7, unless the Agreement sets other values, the defaults are one instalment of 15% of the price plus VAT and deductions of 25% from the stated base. Track the guarantee, use of the advance and annual substantiation separately.

47Retention

In the displayed consolidation, retention applies where Performance Security is built by successive deductions; it does not apply mechanically to every contract. The 2023 amendment contains transitional rules that must be checked for existing projects.

The current default is 5% of the stated base up to 5% of the signing Price unless the Agreement specifies otherwise. Half is released after taking-over and the balance after final acceptance under the clause. Track the combined 10% threshold with Performance Security as well. The scanned Agreement model retains historical values; it does not establish identical retention for all projects.

Security: separate legislation and examples

A guarantee instrument or successive deductions

Illustrative example

The Contractor provides an eligible instrument covering the full security required by the Agreement.

  1. For contracts within the HG 965/2023 amendment’s scope, check the constitution method first. Clause 47.1 excludes Retention Money in the listed fully secured situations.
  2. If security is constituted through successive deductions, calculate under clauses 15 and 47 together, including applicable limits and transfers.

Do not automatically add another 5% retention to every guarantee instrument. This example assumes the 2023 rule applies to the contract.

Subclause 47.1 limits retention to contracts where Performance Security is built through successive deductions. Do not mechanically add retention to a contract whose full security is provided through another instrument.

Applying the clause

  • Under 47.2, the default deduction and cap are each 5% unless the Agreement sets other values; half is released after taking over and the balance after final acceptance.
  • Also read the alternative guarantee in 47.3, the combined 10% threshold and transfer mechanism in 47.4, and the transitional provisions of HG 965/2023.

48Price adjustment

Adjustment uses the Contract’s formula and data: fixed coefficient, weights, indices, sources and Base Date. The rule for periods of 365 days or less differs from longer periods, and the Agreement may specify application. An increase in an actual invoice cost does not replace the contractual calculation.

For each Statement, retain the period, eligible base, indices and auditable calculation, including reductions when indices fall. Post-Base-Date changes in Law have a separate mechanism, and double recovery must be avoided. Contractor-attributable delay limits the usable indices; account for the contractual completion date.

The formula, indices and calculation basis

Keep the exact formula, definitions, base date, indices and their source. Check the triggers and application rules in the relevant contract version.

Applying the clause

  • First check Agreement choices and applicability. The polynomial in 48.4 is An = av + m × Mn/Mo + f × Fn/Fo + e × En/Eo; its weights satisfy av + m + f + e = 1.
  • Where 48.3 applies and the adjustment-data table is not completed, 48.5 provides An = av + (1 − av) × In/Io. Retain the index source, Reference Date and 60-day lag for the current index.
  • Separate work valued at Cost or current prices, rules after taking over or expiry of the completion period, and legal changes under 48.8. A single inflation percentage does not reproduce these mechanisms.

49Valuation and payment schedule

The Price is lump sum; the Schedule of Payments states amounts or percentages and conditions for each payable stage. Higher actual effort or cost does not automatically increase the Price, just as the Contractor’s own savings do not automatically reduce it.

The Supervisor also checks actual completed value through the specified alternative method using quantities, measurements and relevant prices. Where the schedule yields a significantly higher value, it may temporarily withhold the substantiated difference. Provisional Sums remain subject to instruction and evidence, not a discretionary Contractor budget.

How the value of work is supported

Annex 2: track the payment schedule and provisional sums.

Applying the clause

  • The price, excluding Provisional Sums, is a lump sum. The Payment Schedule allocates it to parts or phases and defines when they become payable.
  • Use Provisional Sums under the Supervisor’s instructions, with the evidence and procedure required by the contract.

50Interim payments

Payment involves three distinct documents: the Contractor’s Statement of Works, the Supervisor’s Payment Certificate and the invoice. The Statement separates work, adjustment, retention, advances, eligible materials and other sums, with supporting evidence and direct-payment subcontractor allocations. Unincorporated materials have their own conditions; delivery alone does not automatically justify payment.

The Supervisor normally checks and certifies within 30 days; it may correct earlier certificates and withhold the value of unfulfilled obligations under the clause. A proper invoice is a payment condition, not a substitute for certification. Read the project’s actual contractual period and process rather than importing another tender’s terms.

Four stages with separate dates

Illustrative example

The Statement is submitted on one date, certified later and invoiced on another date.

  1. Record receipt of the Statement, issue and receipt of the certificate, the invoice and payment separately.
  2. Calculate each period from the trigger specified in the clause, checking payment conditions and applicable legislation.

Submission of the Statement does not by itself establish the invoice due date. Keeping the stages separate identifies where a delay occurs.

Track four separate stages: the Contractor’s statement, the Supervisor’s review/payment certificate, the invoice and the Employer’s payment.

Applying the clause

  • The monthly file includes work value, adjustment, retention, advance, eligible materials and other additions or deductions. The representative signs the statement, backed by the complete final supporting documents required.
  • The consolidated text provides certification within 30 days of receiving the statement and payment within 30 days of receiving the certificate, subject to 50.4. Invoicing starts from day 15 after certificate issue; without a corresponding invoice, payment is not treated as due.
  • For a project review, record the exact trigger for each period and any applicable legal or contractual rule. Do not substitute a generic 30- or 60-day term for that check.

51Final payment

The Final Statement is due within 45 days of final acceptance approval, with supporting documents and all balances: work, adjustments, retention, advances, materials and other claimed sums. Omitting a sum from the final claims item may lose the contractual route to recovery.

The Supervisor issues the Final Certificate within 30 days of the Statement or its due date. Notify disagreement through the applicable procedure; agreed portions remain payable. The commercial team should reconcile certificates, invoices, payments, claims and subcontractor balances before submission.

Financial close-out

Reconcile the final account with prior payments and unresolved amounts. A total without its documentary trail is insufficient.

Applying the clause

  • Final statement, reconciliation, discharge documents and register of reservations or disputes.

52Direct subcontractor payments

Direct payment requires the Subcontractor’s election and an annex specifying its account and the allocation of each payment component. It divides the contractual payment between Contractor and Subcontractor; it does not increase value or make the Employer a party to every subcontract obligation.

Including subcontract work in the Contractor’s Statement confirms performance. Later corrections may require recovery, including from the Contractor if the Subcontractor fails to repay. A usable direct-payment annex links to items or stages and addresses adjustment, retention and advances, rather than stating only an overall percentage.

Direct payment follows the work

Payment to a subcontractor needs a match between work performed, recognised amounts and contract annexes. Avoid including the same amount twice.

Applying the clause

  • Direct-payment option, confirmations and reconciliation for each subcontractor.

53Late payment

Late-payment interest concerns an amount due but unpaid by the deadline. It is calculated monthly on the outstanding sum from expiry of the payment period until the Employer’s account is debited, using the currency’s applicable reference rate plus 8 percentage points.

The clause requires a detailed invoice within 60 days of full payment. Retain certificate dates, the proper invoice, due date, partial payments and rates used. Interest, suspension and termination are separate remedies with distinct conditions and deadlines.

Interest has a starting date

Interest calculation starts with the due date and the unpaid amount. Keep certificate, invoice and payment dates separate.

Applying the clause

  • Due-date schedule, partial payments, applicable rate and period-by-period calculation.

54Third-party payments

The Employer pays third parties only through a compliant assignment or direct payment to Subcontractors. A simple request to change the payee is insufficient.

Where a legal attachment affects payment, resumption follows notice that the impediment has definitively ceased and the clause’s 30-day period, without prejudice to the interest rule. Record the legal instrument, affected sums and when the measure ended.

Payments to other parties

For payment to a third party, identify its basis, documents and effect on the balance due to the Contractor.

Applying the clause

  • Payment recipient, basis, confirmation and reconciliation.

55Additional costs

Additional Costs must be tied to an eligible event, supported by financial/accounting records and claimed in time. Cost excludes profit and a mere risk of expense; any permitted profit comes from the separate provision granting it.

Annex 2 does not repeat Annex 1’s final 55.1 exclusion for events in 35.1(i)–(ii). Nevertheless, time entitlement does not automatically prove every claimed cost: verify the applicable basis, causation, amount and absence of double recovery. Keep design, construction and remobilisation costs distinct.

Additional cost and its basis

An incurred expense is not automatically recoverable. Link the amount to the event, contractual basis and claim procedure.

Applying the clause

  • Separate direct and indirect costs, evidence and checks against double recovery.

56End of parties’ liability

Final acceptance confirms performance of execution, completion and remedy obligations but does not erase outstanding obligations or statutory defect liability. The Contract remains relevant to their nature and extent.

After final payment, financial obligations close under clauses 51 and 56, subject to fraud and deliberate-error exceptions. The close-out record should retain acceptance minutes, reservations, guarantees, quality documents and the final financial position.

What remains after the account is closed

Read financial close-out alongside continuing obligations and preserved claims. Identify any necessary reservation expressly.

Applying the clause

  • Register of surviving obligations, securities, defects and unresolved claims.

CLAUSE GUIDE

From completion to final acceptance

57Acceptance principles

Checks for taking-over or final acceptance take place in the Contractor’s presence. Absence does not prevent them where proper notice was given at least 30 days beforehand.

If weather or exceptional circumstances make checking impossible, the Supervisor records that impossibility and checks follow within 30 days after the impediment ends. This does not excuse presenting the Works in a proper condition.

Distinct acceptance milestones

Tests, taking over at completion and final acceptance are distinct stages. Prepare the documents and owner for each stage in advance.

Applying the clause

  • Acceptance plan with conditions, participants and required documents.

58Tests on completion

Taking-over cannot precede the checks and Tests on Completion required by the Contract. The Contractor gives notice of readiness and provides testing conditions, with specified adjustments where the Employer performs tests.

Failed results lead to repair or reconstruction within the notified period. If the Contractor fails to act, the Employer may intervene at its cost through the contractual procedure. For each test, retain the acceptance criterion, result, defect and retest: “performed” does not mean “passed”.

Evidence that the works function

Completion tests must demonstrate the required result. Plan the method, attendance and response to an unsatisfactory result.

Applying the clause

  • Procedures, notices, results, retests and recorded acceptance.

59Early use

Use of a part before taking-over may transfer responsibility for its care to the Employer and affect penalties for the remainder. Different rules apply where working under continued operation or traffic was specified from the outset.

Record the exact part, condition, use date and whether use is temporary or permanent. Unprovided use causing delay or cost may support a claim. Opening to traffic should not be confused with every consequence of formally approved taking-over.

Use before taking over

Use of part of the works may affect responsibilities and access. Record exactly what is being used and under what conditions.

Applying the clause

  • Use record, physical boundaries, responsibilities and outstanding work.

60Taking over at completion

Taking-over requires compliant work, passed tests and necessary documentary obligations. The Contractor gives at least 15 days’ notice of readiness; the Supervisor checks and makes a reasoned recommendation within 10 days. The Employer organises the committee and communicates its decision with the minutes.

Acceptance should fix the completion date, minor outstanding work, defects and deadlines, and any claims. Suspension or rejection must identify what is needed to resume the process. Taking-over triggers warranty, care and financial-release effects, so vague minutes affect several registers.

For acceptance using Law 141/2026’s special mechanism, check scope and applicable instructions, including article 14’s security consequences. The performance-security section explains this boundary.

Security: separate legislation and examples

Completed works and the acceptance dossier

Illustrative example

The building is physically finished, but some test results and final handover documents are missing.

  1. Reconcile completed works, tests, required documents and any outstanding works or defects in the acceptance checklist.
  2. Under Annex 2, check design deliverables and Contractor’s Documents too. Under both annexes, apply the statutory acceptance regime relevant to the investment.

A photograph of a finished building does not establish every acceptance condition. Payment certification does not replace acceptance either.

Physical completion must be supported by the documents and checks required for taking over. Track outstanding work and recorded defects separately.

Applying the clause

  • Application, construction construction technical record, tests, record and outstanding-action list.

61Defects / warranty period

Warranty covers the Contractor’s design as well as Materials, Plant and workmanship. Track duration and commencement for each accepted part; normal wear and improper use remain distinct from attributable defects.

Annex 2 also provides for warranty-period tests required by the Employer’s Requirements, with their own arrangements and consequences. Plan access, operation, performance measurement, remedies and retesting. A technical performance promised in the Tender must be tested against its contractual criterion, not merely the absence of complaints.

What to track

Check the length and starting date of the warranty/defects period, remedial obligations and extension events.

Applying the clause

  • Reconcile any duration offered for award points with the Agreement. Taking over at completion and final acceptance are separate milestones.

62Final acceptance

Final acceptance follows expiry of warranty, including extensions and the last period for separately accepted parts. The Employer convenes the process and communicates its decision within 5 days after the minutes are signed.

The minutes signed by the Employer certify final acceptance. Suspension or rejection must identify outstanding work and obligations. Approval records completion of obligations and supports security release and the Final Statement, without eliminating liability surviving under the Law.

Closing the defects period

Final acceptance requires review of remedies and remaining obligations. Link the result to releases and close-out documents.

Applying the clause

  • Closed defects register, final documents and release requests.

CLAUSE GUIDE

When the contract departs from the plan

63Breach

Breach means failure to fulfil an obligation, not every disagreement. For Contractor default, the Employer’s notice identifies the obligation and clause, sets a reasonable remedy period and states the procedure invoked.

Use remedies subject to their conditions: recovery measures, withholding, suspension, interest, compensation or termination. A sound record shows the obligation, failure, notice, deadline and response. Informal meeting minutes should not be treated as a termination notice without the required elements.

Breach and remedy

Describe the unperformed obligation, evidence and notice. Choose the contractual remedy based on the actual situation and applicable procedure.

Applying the clause

  • Notices, remedy period, responses and evidence of action.

64Termination by the Employer

Employer termination requires an enumerated ground and reasoned notice received 15 days beforehand. Grounds include unremedied default, unauthorised assignment/subcontracting, bankruptcy, invalid securities or insurance, and the delay-penalty cap. Check the applicable consolidation and date, including repealed provisions.

Termination triggers handover: protecting the Works, inventory, documents, Employer-owned Goods and any assigned subcontracts. The Supervisor values work and sums within the clause’s deadlines. The Employer may complete by other means and reconcile additional costs, distinguishing completed work, remaining scope and costs actually resulting from termination.

Termination by the Employer

Check grounds, notices and consequences separately. At termination, record the state of works, goods and amounts.

Applying the clause

  • Termination file, inventory, measurements, handover and valuation.

65Termination by the Contractor

The Contractor may terminate only on the specified grounds and notice: prolonged nonpayment, Employer obligations unremedied after the required notices, qualifying prolonged suspension or the stated insolvency/bankruptcy events. For Employer default, three notices each allowing at least 30 days to remedy are a concrete requirement.

Contractual handover and valuation follow cessation. Relevant amounts include executed work, Employer-owned Goods, claimed Costs and termination costs/losses within the stated cap. Abandoning the Site should not be assumed to have the effects of validly notified termination.

Termination by the Contractor

Substantiate the grounds and notice before termination. Plan protection of the works, demobilisation and records of the consequences.

Applying the clause

  • Chronology, notices, evidence, costs and state of works at termination.

66Force majeure and unilateral termination

Force majeure requires an exceptional, unforeseeable event beyond control that prevents performance and cannot be overcome through diligence. Notify its nature, likely duration and effects, and continue what can reasonably be performed. Labelling an event does not establish impossibility for every activity.

The clause separately addresses prolonged-force-majeure termination, unilateral termination by the Employer and other impossibility or illegality cases. Earlier breach rights survive and work, Goods and costs are reconciled for the applicable case. Convenience termination is not the same procedure as termination for Contractor default.

Extraordinary events and termination

Force majeure and unilateral termination have different bases and effects. Identify the event, notices and continuing obligations.

Applying the clause

  • Event evidence, mitigation, affected periods and instructions.

67Insolvency

Insolvency affecting a joint-venture member, Subcontractor or supporting third party requires assessment of delivery impact. Following the Supervisor’s notice, the Contractor has 30 days to submit an analysis and a plan to prevent adverse effects.

For joint ventures, the clause permits specified reallocations and leader changes, and in bankruptcy measures concerning the affected member, within its limits and without erasing joint and several liability. Explain who takes over resources, activities and obligations; merely stating that work continues is insufficient.

Continuity when insolvency arises

A party’s financial position may affect continuation. Check official records and the applicable procedure before concluding that the contract has ended.

Applying the clause

  • Official records, notices, representation and measures protecting the works.

68Risk allocation and indemnities

The Employer’s risk list allocates consequences of events such as late access, noncontractual instructions, specified design/data errors, unforeseeable physical conditions, discoveries and qualifying suspensions. The annexes differ: in design and build, the Contractor’s own design and quantity risk do not automatically pass to the Employer.

Consequences must be claimed and evidenced; a listed risk does not always produce time, Cost and profit together. Profit is added only where expressly allowed and within the clause’s formula. Contractor risks do not create extra entitlement merely because the commercial outcome is unfavourable.

Who carries the risk

For each event, separate risk allocation, protection duties, insurance and indemnity entitlement. They do not automatically coincide.

Applying the clause

  • Matrix: event, responsible party, clause, notice and consequence.

69Claims and decisions

Clause 69 is the heading for the mechanism developed in 69a, 69b and 69c: Contractor claims, Employer claims and the Supervisor’s Decision. Keep these stages distinct.

Open the relevant clause for notice and particulars, then track admission in principle, decision and any disagreement. The register should show the event, deadlines, submissions and status of each claim.

The route of a claim

Contractor claims, Employer claims and the Supervisor’s decision have distinct steps. Track each step, not only the amount claimed.

Applying the clause

  • Combined register of notices, particulars, responses, decisions and disagreements.

69aContractor claims

The Contractor notifies the event and contractual basis within 30 days of occurrence, then supplies particulars within 30 days of notice, subject to the specified extension rules. Late notice and missing particulars have different consequences; do not reduce them to a generic “30-day rule”.

A claim should be understandable to someone unfamiliar with the Site: fact, clause, causation, time effect, Cost and records. Continuing events require updates every 30 days and final particulars after they end. Track refusal of an extension and the disagreement window explicitly; retaining emails without deadline control does not itself protect entitlement.

From an event to a substantiated claim

Illustrative example

Required information arrives late and the Contractor considers itself entitled to additional time and cost.

  1. The notice identifies the event, date and contractual basis. Notice and particulars are separate stages with their own time limits.
  2. The particulars connect the event to affected activities and evidenced costs. Track updates and final particulars for continuing effects.

A global amount and a list of problems do not establish causation. Each claimed element must be separately verifiable.

Identify the event, contractual basis, notice and evidence of cost or time impact. Keep contemporaneous records.

Applying the clause

  • The notice identifies the event, date and contractual grounds; the text requires submission within 30 days of the event. Late notice has the time-related consequences defined in 69a.1, rather than one generic rule of total forfeiture.
  • Particulars are due within 30 days of notice, subject to the extension mechanism. For continuing effects, update every 30 days and submit final particulars within 30 days of the end.
  • Separate each claim’s time and financial effects. Include daily records, a revised programme for extension claims, and distinct execution, site-overhead and other costs. Failure to meet substantiation requirements can lead to loss of entitlement under the text.

69bEmployer claims

The Employer has its own procedure for compensation and warranty extension: notify the event, breached obligation and clause within the stated period, then provide particulars. A separate rule applies where it proves it was unaware of the event.

This claim also requires evidence and calculation, updates for continuing events and final particulars. Withholding a sum does not automatically replace the procedure. The Contractor should track receipt, basis, evidence and response or disagreement deadlines, not merely the amount deducted.

The Employer’s claim

The basis and calculation of a claim must be traceable. Link the Contractor’s response to evidence and the decision procedure.

Applying the clause

  • Notice, calculation, evidence, response and decision calendar.

69cSupervisor decision

The Supervisor first checks procedural compliance and contractual merit: admission or rejection in principle is due within 30 days after final particulars. Silence is treated as rejection in principle, with a 10-day disagreement window. Admission does not yet determine the amount or days.

The Decision follows its own examination and consultation stage; a disagreement notice must identify its basis, disputed matters and reasons within the applicable period. Consequences and implementation of decisions on the two Parties’ claims are not identical. Track admission, decision, implementation, payment and dispute separately.

A reasoned decision and the next step

Track consultation, reasons and delivery of the decision. If there is disagreement, the notice deadline and form become critical.

Applying the clause

  • Decision file, receipt evidence and deadline for the next step.

70Disputes and arbitration

A dispute may arise from a notice of disagreement or, where that stage is not required, a dispute notice. Before arbitration or court proceedings, the Parties must attempt amicable settlement, directly or through mediation, following the clause’s sequence and periods.

The procurement documents identify the chosen route: ordinary courts or arbitration. Not every HG1 contract automatically goes to arbitration. The Agreement and applicable text determine place, language and arbitrator numbers; preserve notices, decisions and evidence of the amicable attempt in the dispute record.

Clause 70.6 still refers to the tribunal’s civil division. That historical wording does not by itself determine today’s competent court: Law 101/2016 article 53 and binding High Court Decision 11/2023 identify the administrative and fiscal division for the execution disputes concerned, filed from 10 September 2022. Check the claim’s subject and filing date, procedural law and any valid arbitration agreement. Do not assume court deadlines stop merely because amicable discussions have begun.

What to track

Check the resolution steps, notices and forum selected in the Agreement, including any arbitration option.

Applying the clause

  • A dispute does not automatically suspend performance duties. Read this clause together with the Supervisor’s decision and governing law.

71Governing law

The default governing law is Romanian law unless the Agreement provides otherwise. A working-language choice or foreign contractor does not itself change that rule.

Governing law, contractual language and dispute forum are three distinct questions. Check them together at project start and keep working translations tied to the contractual version they explain.

The contract within the law

Applicable law may impose rules that prevail over contract wording. Identify the relevant version for the procurement and event.

Applying the clause

  • Register of applicable legislation, effective dates and transitional provisions.

72Control and audit

Authorised bodies may inspect documents, the Site and technical, financial and accounting management, including by audit. The clause permits checks up to 7 years after final payment and requires disclosure of record locations and facilitation of lawful access.

Control rights must extend to Subcontractors and persons working for the Contractor. Archive approved versions, payment trails, performance evidence and purchases with an index and controlled access. A pile of PDFs without links between Contract, certificate, invoice and payment makes verification much harder.

An auditable project record

Records should allow decisions and expenditure to be reconstructed. Organise them so someone outside the project can follow the trail.

Applying the clause

  • File index, versions, approvals, costs and access to supporting records.

Specific Conditions and Contract Agreement

The General Conditions are presented clause by clause above. Below are the customisation rules and the Agreement form, separately, so you can find the project parameters quickly.

Official annex source

Important information

This guide provides general information, not legal advice or an assessment of your contract. The explanations and English translation are unofficial. Check the official Romanian text, applicable version and transitional rules for your procedure and project. Examples are not official rulings; consult a qualified lawyer for legal decisions and the responsible professional for technical matters.