Skip to content
WorkStudio Help Home
Knowledge Hub

CATUC: Romanian Permits and Project Documents

CATUC explained through procedures and examples: design documents, notification and permits, November balcony instructions and pending proposals, with dated history and sources.

Open Knowledge Hub ↗

Information only — not legal advice.

English · Editorial and source review: 11 November 2026.

What is new? Ministerial instructions on enclosed balconies were published on 6 November, and OAR published a temporary registration procedure for notification projects on 9 November. Separately, Parliament is considering several proposals to amend CATUC. Those proposals are not yet law.

  • Applicable rules: CATUC generally took effect on 25 August 2026. The text consulted includes the 14 October rectification. MDLPA Order 1389/2026 is published and applicable from 6 November; its instructions explain balcony regularisation without amending the Code’s text.
  • Explanations and professional procedures: MDLPA’s answers of 22 September and 20 October explain the law’s application. OAR’s November communication concerns professional project registration. These documents are not laws amending CATUC.
  • Proposed changes: site-coverage calculations, certain planning procedures, sanctions and owner-built works are the subjects of separate initiatives. The final section explains the present position, each proposal and its possible effect on a project.

Consolidated Code; Order 1389/2026; OAR communication; explained history, with dates and status.

Explained change history — checked on 11 November 2026

November 2026 — what was issued and what effect does it have?

Checked on 11 November 2026 — publication, status and practical consequence
Date and documentIs it in force?What it adds and why it matters
10 November — opinion on B543/2026No. The proposal remains in the parliamentary process.The initiative would allow notification for certain places of worship up to 130 m², including in protected natural areas. The Legislative Council’s favourable opinion contains important observations; it does not introduce the proposed exemption.
9 November — L638/2026, formerly B576No. Urgent procedure, in Senate committees.Proposes a corrected site-coverage definition (POT), clearer building rights and transitional rules, treatment of annulled planning documents and sanctions. The report is due on 16 November; that is not a commencement date.
9 November — L601/2026, formerly B500No. Rejected by the Senate and sent to the Chamber of Deputies.Expanded owner-built works remain a proposal. The Chamber of Deputies is the deciding chamber; rejection by the first chamber does not itself end the process.
9 November — OAR communication, letter 1241 of 6 NovemberTemporary professional procedure; no amendment to the law.For registration evidence for a notification project, OAR recommends uploading the notification instead of the urbanism certificate. Registration evidence does not replace the municipal procedure.
6 November — publication of MDLPA Order 1389 of 5 November, Gazette 932Yes, published ministerial instructions; no amendment to the Code’s text.Explains enclosed balconies: taxation, regularisation, charges and limitation. It does not grant automatic legalisation or remove applicable technical conditions.
2 and 9 November — additional sponsors for L597/2026, formerly B541No. The initiative is in Senate committees.Proposes separate changes to planning approvals, design changes, sanctions and POT. It is distinct from L638, with its own text and legislative progress.
2 November — Cluj County Council proposalsNo. Institutional position and request for legislative action.Raises eight implementation issues, including POT, building rights, sanctions and digital implementation. The council’s request does not change clients’ obligations.

Sources: L638 — progress; L597 — text; L601 — transmission following rejection; B543 — progress; B543 opinion; OAR; Order 1389; Official Gazette 932; Cluj County Council.

The earlier entries below retain each publication’s context. The current explanations of balconies and project registration have been updated in the article itself.

20 October 2026 — MDLPA's second clarification set

The six answers explain existing provisions. The date is the ministry's publication date, not the commencement of new legislation.

The 20 October clarifications — practical effects
QuestionMinistry explanationProject consequence
1. Regularisation chargesThe tenfold multiplier in Article 301(8) applies only to the situation in paragraph (7).It does not automatically apply to houses and other buildings eligible under paragraph (2). Eligibility and supporting documents still matter.
2. Owner-built workNew buildings, interventions and fit-outs have different rules; the permit date also matters.Building a new house differs from repairing an existing one. Article 279(1) allows owner-built garages, terraces and ground-floor outbuildings in urban areas; its ground-floor-house provision is limited to rural areas.
3. Feasibility studiesThe SF justifies the investment in stage 1; design starts in stage 2.SF establishes the site, scenario, cost and performance basis without solution-design plans, sections or elevations.
4. Approval and design competitionsTechnical-economic indicators are approved before design; the concept belongs to stage 2.The ministry recommends a concept competition after approval of the indicators. The SF precedes and supports the competition.
5. Transition from HG 907/2016Investments protected by Article 577(1) retain the regime under paragraph (2). Other investments follow the new stages.Earlier cost-data sources may be used under Article 577(4) pending the reference-index application. That does not restore solution design to the SF.
6. Professional attestationThe letters listing fundamental requirements in Article 386 do not replace the professional codes in Order 817/2021.Attestations are not automatically renumbered. The new external-emissions requirement is distinct from a specialist's attested professional field.

MDLPA, second clarification set; publication date.

14 October 2026 — corrections published in the Official Gazette

Official Gazette no. 862, pages 14–16, contains 74 corrections. The selection below explains 14 topics relevant to design, permitting, construction and use. Rectification removes material errors; under article 71 of Law 24/2000, it cannot change the substance of the law.

Rectification published 14 October 2026 — the problem corrected and its practical meaning
TopicWhat the correction meansCATUC reference
Setting up integrated approval commissionsAuthorities have 45 working days from publication to organise the commissions, replacing 60 from commencement. This is an institutional setup deadline, not the time allowed to decide a building application.Art. 92(10)
The opinion required to initiate planningThe exception to the rule on making one approval dependent on another now names the initiation opinion, replacing the former opportunity opinion. The corrected name identifies the procedure concerned.Art. 89(9)(a)
Converting an existing building’s atticRemoving a comma makes clear that the planning-document exemption concerns attics of existing buildings, including an increase beyond the permitted floor-area ratio through that conversion. It does not exempt every alteration to an existing building or remove the applicable works procedure.Art. 252(f)
Clarifying an incomplete permit applicationReferences to article 281, concerning interventions to existing buildings, are replaced by article 271 and its relevant paragraphs on examining the application and requesting clarification or missing documents. The corrected reference identifies the procedure for an incomplete file.Art. 272(1), (4), (7)
Who checks the technical execution designThe original reference led to article 519 on site insurance. The correct reference is article 440: design checking by attested specialists independent of the design authors, with levels and exceptions depending on the consequence class. The requirement concerns design safety and compliance, not an insurance policy.Art. 277(1)
The designer’s mandatory technical assistanceThe required activities are those listed in article 426(1)(e), (h), (i), (j), (k). The original reference to article 437 pointed to technical expert assessment. The correction identifies the designer duties to include in the commissioned services.Art. 424(2)
Responsibility for checking normal-importance projectsFor checking level 2, the correct reference is article 442(4): the qualitative check of design assumptions, solutions and documentation. The former article 452(4) reference concerned the general contractor. Checking levels and consequence classes are explained in the article below.Art. 446(2)(a)
Dealing with defects during constructionThe control duty now points to article 521 on technical assistance during execution, rather than article 514 on pre-start duties. It directs the reader to the relevant procedure for problems found while building.Art. 466(4)(h)
Estimating the selected feasibility optionInvestment costs for the preferred option follow article 546 on cost estimation. The former reference to article 554 concerned project information exchange. The correction identifies the basis for the estimate; it does not itself alter the investment amount.Art. 496(3)
The building record and monitoring in useCorrect references are article 529 for the building’s technical record and article 550(19)–(21) for monitoring and periodic assessment. They replace references to end-of-use matters and construction products, helping owners locate the relevant records and checks.Art. 407(1); 536(8)
Who retains and updates the technical recordThe duty that other beneficiaries may fulfil by contract is the owner’s duty in paragraph (4): retaining and keeping the documentation up to date. The previous reference to paragraph (3) concerned the site supervisor’s coordination during construction.Art. 530(5)
The scope of periodic assessmentThe corrected wording adds “or”: assessment may concern the whole building or some of its subsystems. The original wording did not clearly express that alternative.Art. 550(21)(c)
The offence of failing to engage required specialistsThe offence is consultants’ failure to engage the specialists required in the situation covered by the provision. The original wording, “engaging”, reversed the meaning of the duty.Art. 570(1)(z)
The future transfer of certain Bucharest permitting powersReferences change from articles 132 and 134 to 131 and 133, identifying powers transferred from sector mayors to the General Mayor. The transfer date remains 1 November 2028; the correction does not bring it forward.Art. 584(2)

Monitorul Oficial / Official Gazette; Legea / Law 24/2000, art. 71.

22 September 2026 — MDLPA’s 15 clarifications

This table summarises the ministry’s answers. The date records publication of the explanations, not commencement of new rules.

MDLPA guidance published 22 September 2026 — the question and the ministry’s explanation
Question in the sourceTopicWhat MDLPA explains
1Pending applicationsApplications registered by 24 August 2026 use the legislation and forms applicable at registration. The ministry explains the move to new forms; Order 975/2026 separately makes them mandatory from publication on 26 August and protects applications preceding the Order.
2Forms during transitionAn older urbanism certificate can support a new application using the new form. Extensions use the separate new application form and are recorded on the original document.
3Approval of detailed planning documentsA previously examined detailed urban plan may use the Code’s mayoral-order approval mechanism for a detailed urban project, if complete and compliant. Cases reserved to the county council president are excluded.
4When privately initiated planning beginsFor planning documents initiated by private persons, the ministry treats the urbanism certificate’s issue date as the initiation date. That date helps determine the transitional regime.
5Continuity of local-authority staffChanges to eligibility requirements do not interrupt existing officials’ work. In the situations described, the Administrative Code allows up to 36 months to take the steps needed to meet the new conditions.
6Chief architect office and professional signing rightsProfessional signing rights in architecture or planning are not a general condition for holding the chief architect office. Actually preparing specialist documentation remains subject to its own professional requirements.
7Calculating plot coverageFor planning documents approved before 25 August and still valid, the ministry retains the calculation rules underlying their approval. It also announces correction of an error in the new definition. That announced correction is not included in the 14 October rectification.
8Extending, replacing or changing a permitAn extension must be requested at least 15 working days before expiry, once, for up to 12 months under article 310(5). Completing unfinished works and changing the design brief follow separate procedures under articles 310(7) and 293.
9Competing planning initiativesRequests to initiate zonal urban plans are published on the authority’s website. Private proposals are coordinated with public-interest investment through reasoned prioritisation.
10The certificate for cadastral operationsMerging and dividing plots inside the built-up area require the cadastral-operations urbanism certificate, with the distinctions explained for apartments and condominiums. Outside that area, operations without a building purpose benefit from an exception supported by the owner’s declaration.
11Subdividing land for housingA two-lot split is a cadastral operation. For 3–12 individual-house plots, a detailed urban project may be used once for the land, subject to compliant access, utilities, services and plots. More than 12 lots or other uses require a zonal urban plan in the guidance.
12Certification of unauthorised buildingsCases under former article 37(6) of Law 50/1991 require planning compliance checks and relevant technical expert assessments. Remedial works may need authorisation; an expert report does not automatically legalise the building.
13Older buildings and land registrationBuildings completed before 1 August 2001 retain the Law 7/1996 route based on the fiscal certificate. Lawfully issued pre-CATUC building certificates remain usable; new regularisation applications follow article 301’s conditions.
14Building on another person’s landThe ministry reads building rights together with the Civil Code, including superficies: the right to own or build a construction on another person’s land. The constituting instrument and the scope of that right matter.
15Connecting to existing public utility networksConnections on public land use the road administrator’s consent/permit. For new buildings this is coordinated with approval of construction; existing buildings do not require concurrent issue. Connections within private property are treated separately.

Announced correction, not adopted by these publications: answer 7 announces a correction to the definition of POT, the plot-coverage percentage. The 14 October rectification does not contain that correction. The ministry’s interpretation for older planning documents is separate from this announced intention. MDLPA.

1. What does CATUC change for a construction project?

Romania’s Code of Spatial Planning, Urbanism and Construction — CATUC — brings together rules for planning, permitting and delivering construction. Law 169/2026 was published in Official Gazette no. 661 on 10 August 2026; its general commencement date is 25 August 2026. Article 575 states that implementation is not conditional on subsequent legislation being adopted.

For a client or design team, the changes affect several concrete decisions:

  • The procedure for the works: alongside building authorisation, the Code defines notification for specified categories, exempt works and a placement opinion for certain installations. The following sections explain these routes with examples.
  • The required documentation: the design submitted for permission and the design used to build have different purposes and contents. Receiving permission does not complete the design process.
  • Design checking: the intensity of checking reflects the consequences of a possible failure. The construction’s risk classification matters, as well as its size.
  • Projects already under way: earlier certificates, applications and investments may benefit from transitional provisions. A new application form does not automatically restart the entire project under new rules.

The Code repeals Laws 50/1991 and 350/2001 and only specified parts of Law 10/1995 on construction quality. Transitional provisions preserve earlier rules in the situations explained below. CATUC, articles 575–583; legislative record.

The terms used in project documentation

  • The urbanism certificate identifies the land or building’s legal and planning position and the procedure’s requirements. It does not permit construction to start.
  • PAC — proiectul pentru autorizarea construirii — is the design submitted for building authorisation.
  • PTh — proiectul tehnic de execuție — is the technical execution design, developing the solutions, calculations, specifications and drawings needed to build.
  • DE — detaliile de execuție — are execution details explaining how elements, connections and assemblies are constructed.
  • PUD — proiectul urbanistic de detaliu, previously the detailed urban plan, and PUZ — planul urbanistic zonal, the zonal urban plan, are planning documents with distinct purposes and approval arrangements.

What are consequence classes and checking levels?

A consequence class describes the seriousness of a failure’s effects on life and health, and its economic, cultural, social and environmental impact. The designer assigns the class using the Code’s criteria and the most severe consequences. A small floor area does not determine the class on its own.

Consequence classes and design checking — CATUC, articles 370 and 440–444
ClassMeaningChecking regime
CC1Construction of reduced importanceLevel 1: designers retain responsibility, without the mandatory independent checking required for higher classes.
CC2Construction of normal importanceLevel 2: independent qualitative checking of assumptions, solutions, documentation and compliance with applicable requirements.
CC3Construction of special importanceLevel 3: checking also includes quantitative analysis of calculation models, sizing and consistency between calculations and drawings.
CC4Construction of exceptional or vital importanceLevel 4: checking includes parallel independent calculations.

The Code abbreviates these design checking levels as NVP1–NVP4. Where independent checking is required, the checkers are attested specialists other than the design authors. Monuments and special procedures have additional requirements to consider. CATUC, articles 370 and 440–445.

A building requirement and a verifier's attested field are different

Article 386 lists fundamental requirements using letters a)–h). These letters are not the professional attestation codes in Order 817/2021. MDLPA explains that commencement of the Code does not automatically renumber verifiers' or experts' attestations. The new external-emissions requirement must be addressed within the project; matching letters alone does not create a new professional competence. Select the specialist by their actual attested field/subfield and current right to practise. MDLPA, answer 6, published 20 October 2026.

2. What happens to projects started before 25 August 2026?

The Code’s commencement does not automatically cancel existing documents or require every project to restart. Transitional provisions determine what continues under earlier rules and which new requirements apply at the next stage. Both the type of procedure and the dates of its documents matter.

Existing certificates and pending applications

Article 582 preserves the validity of earlier urbanism certificates and the former regime for planning procedures started before the Code. Permits based on earlier certificates follow the approval requirements and regulations applicable when those certificates were issued, subject to the article’s conditions. If responsibility has changed, the newly competent authority issues the document.

MDLPA explains the choice of form separately. The form is the administrative vehicle for the application; the applicable legal regime determines how the project is assessed. These can come from different points in time.

A project started before CATUC — what continues and which form is used
SituationTreatment explained by MDLPA
Application registered on 20 August 2026 and still pendingThe legislation and forms applicable at registration are used, with the transitional legal basis identified.
Application submitted on 10 September using a valid urbanism certificate issued in JulyThe new form is used. It does not displace the substantive regime preserved by article 582 for that procedure.
Extension requested after 25 August for an earlier permitThe new extension application form is used; the approved extension is recorded on the original permit.
Planning documentation initiated by a private personThe ministry treats the urbanism certificate’s issue date as the date the procedure began.

For example, a client who obtained a certificate in July and applies for permission in September should not confuse a change of form with expiry of that certificate. Assessment begins with the existing certificate and the applicable transitional conditions. CATUC, article 582; MDLPA, answers 1–4, 22 September 2026.

The forms have their own legal basis and date. MDLPA Order 975 of 25 August 2026, published on 26 August, adopts the certificate, authorisation, amendment, regularisation and notification forms. They become mandatory on publication; Article 3(3) retains the forms valid when applications were submitted before the Order. Each form has an identifier and version. Paper and digital forms are accepted, and local platforms must be updated by 30 December 2026. This distinction particularly matters for applications around 25–26 August: the Code and the Order have different commencement dates. Order 975/2026; form annexes.

Proposal tracked on 11 November: L638 would also clarify certificates requested before commencement. Its proposed wording does not yet replace the transitional rules explained here. The final section compares the positions.

Public investments prepared under Government Decision 907/2016

Article 577 preserves earlier rules on project stages and documentation content for specified public investments. Its protection concerns the new project-stage provisions in Book II, Part IV. Subject to the article’s conditions, the situations include:

  • investments whose construction was already in progress;
  • procurement for the technical design, feasibility study or intervention-approval documentation already initiated by publication of the notice or invitation;
  • documents already received by the investor/client or submitted for approval;
  • investments with financing already approved;
  • updates to documents previously prepared and received, or submitted for reapproval.

For example, a technical design commissioned through procurement initiated before the Code may continue with the documentation structure preserved by article 577. That provision does not automatically settle other questions, such as which authority issues a document or how an approved design may be changed. Each concerns a separate obligation. CATUC, article 577.

Article 583 maintains earlier implementing regulations until replacement insofar as they do not conflict with the Code. Teams can therefore identify the applicable rule without assuming that every earlier decision and regulation disappeared on 25 August.

Bucharest — transfer of powers on 1 November 2028. Article 584(2), through its corrected references to articles 131 and 133, identifies the powers that will transfer from sector mayors to the General Mayor. The future date is unchanged. Rectified: 14 October 2026 Official Gazette no. 862.

3. Which works require building authorisation?

Building authorisation is the usual route for construction and interventions covered by article 259. The Code separately defines the categories eligible for notification, exemptions and the placement opinion. Classification depends on the actual works, their location and the conditions of the relevant provision.

Typical situations requiring examination under the authorisation procedure include:

  • a new apartment building in an urban area;
  • adding another storey to a house;
  • an extension that does not satisfy a simplified procedure’s conditions;
  • changing the position or footprint of an already authorised building, requiring consideration of a modification permit.

The urbanism certificate establishes the planning context and required approvals. The right to start works follows completion of the applicable procedure, rather than obtaining the certificate or a utility provider’s approval alone.

What belongs in the application file?

Article 262 requires documents identifying the applicant, building right, design and conditions for approval. Depending on the works, the file includes:

  • The application and property identification: current cadastral-plan and land-register extracts, normally no more than 30 days old, subject to statutory exceptions.
  • The building right: evidence of the right where required.
  • The design for building authorisation — PAC and, for buildings, evidence that the project has been recorded with the Romanian Order of Architects.
  • Applicable approvals and consents, including environmental documents. Where tacit approval is relied on, the declaration required by the Code is included.
  • Neighbouring-property and safety documents: the expert assessment or measures to make the site safe, where required.
  • Documentation for the road administrator, where relevant.
  • Investment information: the general estimate, value and duration.
  • Design checking reports, according to the applicable checking regime.

The documentation section below explains PAC, which is one part of the application file. CATUC, articles 253, 259 and 262–264.

If the design changes during construction

Moving the building on the plot or changing its footprint may require a modification permit under article 293. Before executing the changed design, the team establishes whether it remains within the existing approvals and planning conditions or requires new approvals. Certain local technical modifications may use the designer’s site instruction, subject to the Code’s specific conditions. Moving the entire building, for example, cannot be treated simply as an updated drawing or digital model. CATUC, article 293.

4. Which works can use prior notification?

Prior notification is the simplified procedure through which the client formally informs the competent local authority of intended construction work. For the categories and conditions specified in article 294, work may follow this route without the ordinary building-permit procedure. By submitting the notification, the client declares on their own responsibility that the legal conditions for using this procedure are satisfied.

In practice, the procedure involves:

  • Submission before work starts: the holder of the relevant right over the property sends the notification form to the competent local authority, on paper or digitally.
  • A design and supporting documents: the form is accompanied by a simplified technical execution design (PTh), prepared by competent specialists, payment of the prescribed fees and any additional documents required for the particular situation.
  • Assessment by the authority: it may request missing information or approvals, determine that a building permit is required, or reject the notification with reasons. Article 296 also provides for tacit approval taking effect after 15 working days from receipt, subject to its conditions.
  • Observing the start date: acknowledgement of receipt does not allow an immediate start. For tacit approval, article 296(6) requires a further 15 calendar days after the 15-working-day period; any requested information or other conditions must be fulfilled under the procedure. Section 5 explains the timing.

For example, the owner of an eligible rural house submits the form with the simplified design and other required documents, then completes the assessment stage and statutory waiting period before opening the site. A letter asking the municipality whether a permit is needed does not count as notification. The client, designers and contractors retain their respective responsibilities. CATUC, articles 294–298.

The examples below show which works may qualify and the limits that apply.

OAR registration evidence for notification projects

Updated following OAR’s communication published on 9 November 2026. Notification simplifies the administrative route, but the design still requires the professionals specified by law. OAR—the Romanian Order of Architects—explains that project-registration evidence is also required for these projects.

  • The architect requests project-registration evidence, holding valid signing rights for the relevant activity.
  • As a temporary arrangement, OAR recommends uploading the notification instead of the urbanism certificate when requesting that evidence.
  • The evidence concerns professional registration. The client must separately satisfy the municipal notification requirements and the conditions for starting work.

Example: for an eligible rural house, the architect uses OAR’s temporary procedure to obtain registration evidence. Receiving it does not mean the owner may open the site that same day. OAR, letter 1241 of 6 November, published on 9 November.

Rural single-family house up to 150 m²

Article 294(2)(a)(ii): a single-family house on its own plot with its own access, in rural intravilan outside protected areas and monument-protection zones, may qualify if it has ground floor only or demisol plus ground floor, no subsol, and no more than 150 m² total floor area. The text also requires the prescribed type-project or individually designed route, competent architecture/structure/services designers, respect for the relevant rural architecture guide and county chief-architect approval. A 145 m² house with an upper storey or basement does not qualify through this subpoint merely because it is under 150 m².

Rural outbuildings

Article 294(2)(a)(i): garages, covered terraces, pergolas, summer kitchens, kiosks, pools and similar external single-family accessories may qualify within a cumulative 50 m² limit, including permanent structures with foundations below 20 m². This subpoint excludes rural localities in metropolitan areas and has the rural-intravilan, protection and planning conditions stated in the article. An 18 m² structure with foundations should therefore not be labelled “exempt under the 20 m² rule” without checking the separate criteria.

Existing buildings outside protected areas

Article 294(2)(b): roof replacement may retain the shape or reconfigure it with a rise of no more than 0.50 m, while respecting permitted ridge/eaves heights; an attic may be fitted out in a single-family house within its unchanged volume without strengthening works; certain nonstructural repartitioning and uniform balcony enclosures are listed. The provisions also include extensions for sanitary or technical spaces up to 25 m². Each example keeps the conditions attached to its own subpoint.

Converting an attic also raises a separate urban-planning question. Article 252(f), as rectified, concerns bringing attics in existing buildings into use, including where the regulated CUT is exceeded, without new urban-planning documentation. The works must still follow the applicable authorisation, notification or exemption conditions. For example, eligibility for notification cannot be established from the CUT exception alone.

Rectified: 14 October 2026. Monitorul Oficial no. 862, pp. 14–16.

For demountable lightweight partitions, the notification category requires no effect on evacuation-route lengths or widths, fire-protection installations or fire stability. A partition that narrows an escape route is not automatically eligible simply because it is lightweight. Changes to commercial or office use with public access are listed only where they do not involve other works requiring authorisation and comply with planning rules.

Protected-area work requires separate attention. Article 294(3) establishes a narrower route for specified repairs, with eligibility dependent on the building's classification and architectural/historic status. It requires notification to both the local authority and the culture service and the culture service's written agreement stating conditions and deadlines. Examples include minor exterior-finish repairs retaining material, colour and texture, and exterior joinery repairs retaining the specified material, form and dimensions. Establish eligibility under the actual heritage provisions before choosing this route. Ordinary repair examples cannot be transferred indiscriminately to a monument or a protected setting. CATUC, art. 294.

5. When can work start after notification?

Under article 296(1), tacit approval takes effect after fifteen working days from receipt. The authority may instead request clarification or missing documents, require complementary approvals, identify the need for a building authorisation or reject noncompliant works. Article 296(6) then states that works start fifteen calendar days after expiry of the tacit-approval period, or after full satisfaction of the applicable conditions. Articles 297–298 retain design, quality and responsibility requirements. It is inaccurate to turn this into “start on working day sixteen” or “thirty working days”.

Example: an owner submits a complete notification on a Monday. The team records receipt, calculates the working-day period with public holidays, checks any response and then applies the additional calendar-day period. The calendar depends on actual receipt and the procedure’s subsequent events; a generic online countdown is not evidence of entitlement to start.

Article 298 provides its own technical-verification regime, placing design responsibility on the relevant designers. It expressly requires geotechnical and topographic studies for adapting the qualifying rural-house type project to its site. Receipt at completion includes the contractor, beneficiary and a local-authority representative. Until the National Construction Register is operational, the article provides transmission of the receipt record to ISC. Simplified authorisation does not mean undocumented construction. CATUC, arts. 295–298.

6. Which works are exempt from authorisation and notification?

Article 299 lists works without building authorisation or the formal notification procedure, subject to the conditions and exceptions within the article. For the ordinary examples outside protected areas and monument-protection zones, it includes interior plastering, painting and floor finishes; interior joinery; repairs to fences retaining their form and materials; roof repairs retaining form and appearance; and exterior joinery replacement retaining the openings’ form and dimensions, even where the joinery material changes. Exterior repainting retains the specified façade elements and colours. Changing a window opening or substantially changing a roof is a different factual case.

A rural demountable-outbuilding example under article 299(2)(c) combines a cumulative maximum of 20 m², maximum height of 2.5 m, no foundations, temporary/demountable construction and the stated timber/metal and planning conditions. A hypothetical 18 m², 2.4 m-high demountable timber accessory without foundations may fit if all other conditions are met. Adding foundations removes it from that particular exemption; it may need notification or authorisation under the separate provisions. Article 299 also contains declaration/tax obligations for temporary annexes.

Photovoltaic example: article 299(2)(a), point 13, addresses solar systems and prosumer photovoltaic systems but expressly requires prior information to the local authority and a supporting structure able to take the applicable dead, wind and snow loads. The article’s “no formalities” heading must not erase that specific condition. Environmental, heritage, planning, quality and other applicable sector rules continue to matter, as do the receipt and technical-record duties prescribed by the article. CATUC, art. 299.

7. A separate route: aviz de amplasare

Article 300 provides placement approval for specified installations, including bicycle racks, electric-vehicle charging points and certain recycling or sanitary facilities. It has its own siting, circulation and utility conditions. A charging point falling within this provision may not need the ordinary building-authorisation procedure, but it is not thereby in the category “install without any administrative step”. First distinguish authorisation, notification, exemption and placement approval, then examine the exact project. CATUC, art. 300.

Owner-built work and regularisation: two important distinctions

Owner-built work describes how the work is organised; it does not provide a general exemption from design or administrative procedures. The second MDLPA clarification explains:

  • For new buildings requiring authorisation, Article 279(1) permits owner-built garages, terraces and ground-floor outbuildings in urban and rural areas; its ground-floor-house provision is limited to rural areas.
  • For interventions to existing buildings, Article 285(1) limits owner-built work to maintenance and routine repairs in both settings. Fit-outs have specific rules under Articles 292(2) and 298(4).
  • Permits issued before the Code retain the execution-method rules applicable when issued. Execution requires technical design, subject to exceptions in the Code or applicable former legislation.
  • Article 301(8)'s tenfold increase in charges and ISC contributions applies to paragraph (7), not automatically to eligible categories under paragraph (2). Regularisation still requires the legal conditions to be met; paying a charge is not sufficient.

For example, a house meeting Article 301(2)'s criteria does not automatically attract the multiplier applicable to other categories. Separately, eligibility for owner-built work does not settle whether authorisation or notification is needed. MDLPA, answers 1–2. Clarification: 20 October 2026.

Existing enclosed balconies: what do the November instructions clarify?

Applicable update from 6 November 2026: MDLPA Order 1389/2026, published in Official Gazette 932. The instructions seek consistent application of article 301 to enclosed balconies in lawfully built apartment buildings. Their role is administrative and interpretative; they do not rewrite the Code.

  • The building and the alteration are considered separately. Enclosing a balcony does not, by itself, turn the entire lawfully constructed building into an unlawful building. The order rejects automatic application of article 301(11)’s 100% property-tax increase on that basis alone.
  • Regularisation may use the permanent route. For enclosures meeting the conditions explained in the order, without a ground-floor extension onto public land, the ministry points to article 301(2). That route is not limited to 25 August 2027, the deadline for the temporary mechanism in paragraph (7).
  • Charges are not automatically multiplied by ten. The increase in paragraph (8) is linked to the paragraph (7) mechanism, rather than every balcony application. Charges and contributions due under the applicable regime remain payable.
  • Technical compliance remains necessary. The application, expert assessments and legal conditions for regularisation must still be satisfied. Paying charges or demonstrating an alteration’s age does not itself legalise it.

Example: a third-floor apartment in a lawfully built block has an enclosed balcony, without extending the building’s footprint onto public land. The order explains why this should not automatically be treated as an entire unauthorised building, and why the 25 August 2027 deadline and tenfold charge do not automatically carry across to the application. The authority and responsible professionals must still establish eligibility and the required documentation. A new ground-floor space built over a pavement requires a different assessment.

Three years or five: which period concerns the sanction?

The order sets out an interpretation concerning a three-year limitation period from completion and states that the new Code cannot revive the sanctioning of conduct already time-barred. Limitation of a sanction and the legality of construction are nevertheless different questions.

  • The completion date and the law applicable to the conduct must be established from the evidence and circumstances.
  • Older works and works carried out after CATUC took effect may require different analysis; the rules on more favourable contraventional law also matter.
  • A five-year period appears in proposal L638 for the fines identified in article 357(4). On 11 November it is not a new rule in force and cannot be presented as a general period for every construction offence.

Consequently, the fact that a balcony was enclosed more than three years ago is not, by itself, a certificate of legality. Limitation, regularisation and technical conditions each require their own assessment. Full order and instructions; Official Gazette publication; CATUC, articles 301, 357 and 581; L638 — proposed text.

8. Which documents are prepared before construction?

The design brief: what the investment must achieve

The design brief establishes the project’s objectives and limits. Articles 490–491 cover:

  • the investment, client and other parties;
  • the site, existing situation and relevant studies or surveys;
  • legal, technical, economic and planning constraints;
  • functions, dimensions, flows and intended quality;
  • utilities, restrictions and budget assumptions.

For an office building, for example, the brief needs to describe users, circulation, accessibility, utilities and site constraints as well as the number of rooms.

The feasibility study: justify the investment before design

The SF answers «is the investment justified, where, and within what cost, performance and time limits?» In the new life cycle it belongs to initiation, stage 1. It does not determine the building's architectural form. MDLPA's 20 October clarification explains this distinction through Articles 478–479 and 492–496.

  • Investment analysis: need, demand, alternative sites and comparable scenarios, economic and financial feasibility, sustainability and risk.
  • Functional proposals in principle: accommodation needs and functional relationships, developed through design later.
  • Analytical graphics: location, site comparisons, functional diagrams and area schedules. These differ from plans, sections, elevations and massing for an architectural solution.
  • Cost: an estimate based on the reference index and budget margin under Article 494(3), rather than measured quantities from an already designed solution. Pending the Article 418 application, whose statutory target is 1 September 2027, Article 577(4) permits earlier legal sources for establishing costs.
From need to design — the sequence explained by MDLPA
StageResultExample: a new school
Stage 1: initiation and SFInvestment justification and approval of technical-economic indicators before designEstablish demand for places, the site, estimated budget including margin, performance and duration.
Stage 2: conceptThe first design stage; the accepted concept supports the final design briefDevelop the spatial organisation and architectural concept within the approved parameters.
Design developmentAuthorisation and execution documentation with the content required at each stageDevelop PAC, technical design and details; authorisation does not replace execution design.

For a design competition, the ministry recommends approving the indicators first and using the SF and initial brief as inputs. The winner's subsequent contract may cover concept development and later documents; commissioning the SF through that contract would reverse the recommended sequence.

The exception for investments already under way remains essential: projects meeting Article 577(1) retain the earlier documentation regime. For other projects, HG 907/2016 applies only insofar as compatible with the Code. MDLPA, answers 3–5. Clarification: 20 October 2026.

PAC: the design submitted for building authorisation

Article 503 and Annex 2 organise the authorisation design into site, architecture and engineering documents:

  • Context and existing site: location plan, the prescribed topographic/cadastral survey in the Stereo 70 system and cadastral-office endorsement, neighbouring buildings and heights, access and contextual photographs.
  • Proposed site: what is retained, demolished and built, levels and heights, external works, access and boundaries.
  • Architecture: explanatory memorandum, indicative plans of levels and functions, roof, elevations, sections and contextual representations. The memorandum addresses materials, quality, heritage, access, parking, utilities, waste, neighbours and environmental relationships as applicable.
  • Existing-building interventions: measured surveys and the relevant diagnosis or technical expert assessment. The annex adapts contextual documents for wholly internal interventions.
  • Engineering: discipline memoranda and diagrams, underground connections, checked geotechnical documentation, calculations and drawings differentiated by consequence class.

The class distinctions have practical effects. Annex 2 requires calculation reports for CC3 and CC4, structural and services concept drawings for CC2 and CC3, and the specified formwork/section drawings for CC4 or buildings with more than one underground level, excluding the semi-basement. The classes are explained near the start of this article.

Annex 3 provides a simplified PAC for the specified rural single-family category, with no more than a ground floor and attic and 150 m². This documentation belongs to the authorisation route. Rural-house notification has different conditions: article 294 specifies a ground floor, or semi-basement and ground floor, without a basement, while article 295 requires a simplified technical execution design. A house with an attic does not qualify for notification merely because it is below 150 m². CATUC, articles 490–503 and Annexes 2–3.

9. What is required for construction, site setup and handover?

Technical design and execution details

The technical execution design — PTh — develops the solution that will be built. Articles 505–508 provide for:

  • design memoranda and other written documents by discipline;
  • calculations and justification of the solutions;
  • specifications setting technical requirements for works and products;
  • quantities and economic documents;
  • the programme and monitoring provisions;
  • the architectural, structural and services drawings prescribed for the project.

Execution details — DE, article 509 — add:

  • construction details, connections and assembly solutions;
  • coordination between disciplines;
  • material and equipment characteristics;
  • updates to economic documents and the programme resulting from design development.

For a façade, for example, the general drawing shows the geometry; details must make the connections to floors, openings and roof buildable in accordance with the technical requirements. The guide to BIM, PTh and DE develops the discipline-specific lists and checking and signing conditions.

Article 277(1) refers to article 440 for technical-design checking: attested checkers independent of the design authors, with levels and exceptions corresponding to the consequence class. Rectified: 14 October 2026, replacing the erroneous reference to site insurance. Official Gazette no. 862.

Site setup: design, permission and responsibilities

Site organisation determines how the location operates during construction: access, protection of neighbours, staff facilities, utilities, storage and waste removal. Articles 250 and 516–517 set requirements separate from the building design.

Approvals and documents before work starts:

  • Site organisation requires authorisation. The applicant requests it together with the main works; the contractor may apply separately on the basis of the construction contract.
  • The general contractor prepares the site-organisation design under article 517.
  • The specific utility approvals must be obtained and a contract concluded with a specialised disposal facility for waste removal, as required by the article.
  • Prevention and risk-management plans, site security and protection of neighbouring properties must be prepared and approved.
  • The client prepares the site handover record. The contractor prepares the health, occupational safety and waste-removal plans.

Contents of the site-organisation design under article 517(2):

  • fencing and access;
  • the wheel-washing platform, water collection and prescribed drainage arrangement, with the pressure pump at the entrance;
  • temporary offices, eating facilities and toilets, with construction details where needed;
  • utility networks and connections;
  • fixed and mobile plant;
  • precasting areas where required;
  • material and waste storage;
  • delivery and removal arrangements.

Where a pavement or other public land must be occupied temporarily: the design must include the occupation plan, duration, boundaries of the affected areas, and vegetation and protection measures. Occupation must be strictly necessary for the authorised works; the relevant fees and approvals apply. The contractor obtains the consents for temporary works and restores the land under the arrangements agreed with the authority.

For example, a site accessed from a narrow street must resolve lorry movements, wheel washing, storage and pedestrian protection in its design. If these temporarily occupy the pavement, the area and duration form part of the documentation and required approvals. CATUC, articles 250 and 516–517.

Handover and the building’s technical record

At completion, the documentation must describe the construction delivered and how it is to be used. Articles 528–530 include:

  • the designers’ and site supervisor’s opinions required for acceptance;
  • acceptance records and the building’s technical record;
  • as-built documentation, with responsibilities and detail agreed contractually under the Code;
  • operating and maintenance instructions, component service lives and monitoring;
  • operator training.

The technical record brings together design, construction, acceptance and in-use documentation, including maintenance, repair and monitoring. During construction the site supervisor coordinates updating under article 530(3). The owner retains and updates the documentation under paragraph (4); paragraph (5) allows other beneficiaries to fulfil that latter duty under the contract. The reference to the owner’s duty was corrected by the rectification published on 14 October 2026. CATUC, articles 528–530; Official Gazette no. 862.

Practical cases from the ministry’s 15 clarifications

Interpretation source: MDLPA, 22 September 2026. This section explains the ministry’s position without treating its document as a legislative amendment. Complete clarifications.

Extending a permit or completing unfinished work

For an extension, question 8 points to art. 310(5): apply at least 15 working days before expiry; extension is available once, for up to 12 months, subject to the provision’s conditions and fee. For unfinished works, the ministry points to the new-authorisation route in art. 310(7), with the conditions for proceeding without a new urbanism certificate and new approvals. A change of brief follows art. 293. These are three separate decisions. A late extension request should not be presented as an automatic continuation right. MDLPA, questions 1–4 and 8.

POT: preserve the approved planning basis

The ministry says the new POT definition does not apply to planning documents approved before 25 August 2026 that remain in force. It explains that applying a changed calculation method to an unchanged approved percentage could reduce the permitted development without formally changing the planning regulation. It also identifies a material error in the new definition and states that a correction was being pursued. That statement of intention does not itself replace the wording in the Gazette; the rectification of 14 October contains no correction of POT.

Example. A valid older PUZ sets POT at 30% for a 1,000 m² plot: the numerical limit is 300 m² under the calculation rules supporting that PUZ. Before deciding whether a terrace, projection or other element is included, identify the approved plan, its date and its applicable definition. Do not silently recalculate the same 30% using a different denominator or a newly assumed list of surfaces. Record the designer’s calculation and obtain the competent authority’s position where the basis is disputed. The example illustrates the need to establish the calculation rules; it does not decide which elements are excluded for every project. MDLPA, question 7.

Status update—11 November: L638 and L597 now propose changes to the POT definition, in different forms. Neither is in force. The final comparison explains why the calculation matters and why proposed wording cannot be applied automatically.

Land division: two plots, twelve plots and agricultural land

MDLPA distinguishes a cadastral split from development subdivision. A two-lot split is described as a cadastral operation. A subdivision into 3–12 plots for individual homes can use PUD once on the land when the conditions are met, including access to an existing or planned road, utilities, public services and compliant plot dimensions and shape. More than 12 plots, or another function, calls for PUZ under the explanation. The number of lots alone is insufficient.

Example. Eight proposed house plots beside an existing road are not automatically ready for a PUD: the design must establish access, utility connections, public services and plot compliance. Eight commercial plots cannot borrow the individual-housing route. Splitting agricultural land in extravilan for agricultural use is a different case; the ministry explains the exception from the cadastral urbanism certificate when no construction is intended and requires the owner’s declaration in the instrument or separately.

Question 10 explains that intravilan merging/splitting generally requires a cadastral urbanism certificate, with the stated specific cases. Pre-apartmentation and apartmentation are treated separately from re-apartmentation and sub-apartmentation. For condominium land, check whether the split follows the permit and approved planning documentation, including access, landscaping, parking and project phases. A cadastral operation does not establish a right to build. MDLPA, questions 10–11; CATUC arts. 216–240.

Existing buildings, registration and regularisation

Questions 12–13 distinguish several situations that should not be combined into a promise of retrospective approval. The ministry describes the technical and planning evidence needed for earlier art. 37(6) cases; a favourable outcome depends on compliance, and required corrective works may themselves need authorisation. For new requests after 25 August, it directs readers to the regularisation procedure in art. 301, subject to its conditions.

It also preserves the separate land-registration mechanism under Law 7/1996 for buildings erected before 1 August 2001 without an available permit, using the fiscal certificate as described in the guidance. A construction certificate lawfully issued under former art. 37(6) before CATUC took effect can still support registration. Example: a missing permit for a 1998 building, a certificate issued in July 2026 and an unauthorised extension built in September 2026 require different analyses. The fiscal or cadastral record should not be used to assert structural, fire or planning compliance without the relevant evidence. MDLPA, questions 12–13.

Utility connections and the right to build

For connections to existing public utility networks on public land, question 15 explains the road-administrator agreement/authorisation route. For a new building the required connection approval is coordinated with its authorisation or notification procedure; the ministry says that simultaneous-issue condition does not apply in the same way to an existing building. Connections within private property are addressed separately. The example concerns a connection to an existing network: a network extension, excavation affecting other infrastructure or another independently regulated operation needs its own assessment.

Question 14 discusses superficies and other rights enabling construction on someone else’s land. Record the constituting instrument, its permitted works and the owner’s consent where applicable. The ministry reads art. 245 with the Civil Code; possession or an ordinary right of use should not be treated as equivalent evidence of the right to build. MDLPA, questions 14–15.

Local administration: competence and continuity

Questions 5–6 distinguish the chief architect’s public-office duties from personally preparing professional design documentation. The ministry explains continuity for existing officeholders and the Administrative Code’s conditions, including the 36-month rule for the necessary steps towards new qualification requirements in the circumstances it describes. OAR/RUR signing rights are not presented as a blanket condition for occupying the chief-architect post; the right to prepare particular documents remains a separate issue. Question 9 explains publication and coordination of competing PUZ initiation requests against public-interest priorities. For an applicant, the useful check is the competent authority, the published request and the recorded reasons for prioritisation. MDLPA, questions 5–6 and 9.

10. Questions to resolve for each project

Before submitting documentation or starting work, the client and responsible specialists should be able to answer these questions clearly:

  • Which transitional rules apply, and which dated documents establish that position?
  • Does the land or building have a protected status that changes the procedure?
  • Do the works require authorisation, notification, a placement opinion or an exemption?
  • Which documents are needed, and who prepares and checks them?
  • Which conditions must be met before starting, and which changes need further approval?
  • Who prepares the completion records, and who retains the technical record after handover?

The answers provide the basis for a realistic design and construction programme. For the relationship between digital models, checked drawings and professional signatures, see BIM and execution documentation in Romania.

Which changes are proposed but do not yet apply?

Status checked on 11 November 2026. A bill can be amended, rejected or adopted in a different form. A favourable opinion, urgent procedure or committee deadline does not bring it into force. Application depends on the adopted and published law, its commencement date and transitional provisions.

L638/2026: the current position, proposed change and possible effect

The initiative was initially registered as B576 on 19 October. It received number L638 and urgent procedure on 9 November; at the review date it is in Senate committees. The table explains the proposals most relevant to clients and designers, without incorporating them into the applicable rules above.

L638/2026 explained — every change in the second column is a proposal
Current position and practical issueWhat the bill would changeExample and possible consequence
POT, the percentage of a plot occupied by construction: the Code’s definition lists several outdoor arrangements without the explicit exclusion wording identified by MDLPA. October’s rectification did not correct this point.Annex 1 would expressly exclude the listed arrangements, such as paths and uncovered parking.A 500 m² plot with a 150 m² building and 50 m² of paths illustrates the issue: 30% if only the building counts, 40% if the paths are added. The example explains the calculation difference; it does not independently establish the lawful method for a particular plot.
Entitlement to request permission: building on another person’s land requires consideration of article 245 and the Civil Code. MDLPA has explained its interpretation of superficies.Article 245 and the Annex 1 definition would specify eligible right-holders and the conditions attached to rights supporting an application.Superficies is the right to own or erect a building on another person’s land. Its holder would have a more explicit statutory formulation, but the instrument creating the right and its limits would remain decisive.
Building within an existing frontage: matching neighbouring heights alone does not replace the applicable planning conditions.Article 257 would introduce a case for construction, additional storeys or extensions within an existing frontage, with the stipulated relationship to neighbouring heights, without new planning documentation under the proposed conditions.Filling a gap between two buildings of the same height could follow a simpler planning route. Building permission and other applicable conditions would remain necessary.
An annulled general urban plan—PUG—or missing planning regulation creates difficulties in establishing the basis for permission.Articles 66, 361 and 573 would clarify reinstatement of an earlier PUG, cases with no earlier PUG and use of the General Urban Planning Regulation—RGU—in defined circumstances.If a court annuls the PUG, the existence of an earlier plan and the judgment’s effects must be established. The proposal does not mean unrestricted development after annulment.
Fines and conduct predating the Code require identification of the applicable law and the date of the conduct.Article 357 would specify five years for imposing fines under paragraph (4); other provisions would address earlier conduct and evidence of completion.The inspection date alone would not establish when construction occurred. Old and recent works cannot automatically be treated alike. The Legislative Council calls for care over non-retroactivity and more favourable law.
Transitional urbanism certificates: the current text protects certain certificates issued before the Code; the application date can raise a separate issue.Article 582 would expressly mention certificates requested and/or issued before commencement and clarify subsequent permitting.For an application made in July with a certificate issued in September, the proposal could matter. The applicant cannot currently rely on the proposed wording as an adopted rule.

Full L638 text; parliamentary progress; Legislative Council opinion 918, with observations. The initiative also addresses certain works in protected settings and public-investment funding categories; the exact conditions need to be followed in the text emerging from Parliament.

The other initiatives have different subjects and legislative paths

  • L597/2026, formerly B541: proposes broader changes to approvals and signatures, urban regeneration, sanctions, POT and provisions on informal settlements. A practical example concerns a change to the design brief: the bill would retain unaffected approvals and require written identification of those needing renewal. On 11 November it remains in Senate committees; the displayed first-chamber tacit-adoption deadline is 25 November. This is not a commencement deadline. Proposed text.
  • L601/2026, formerly B500: would expand owner-executed individual housing and regulate the beneficiary-executor role. Professional requirements remain for activities requiring qualification or authorisation. The Senate rejected it on 9 November and sent it to the Chamber of Deputies, which decides. It does not currently authorise an expansion of owner-built works. Text; transmission letter.
  • B543/2026: would add notification for specified places of worship up to 130 m² gross floor area, including in protected natural areas, with environmental derogations. The Economic and Social Council issued a negative opinion; the Legislative Council opinion received on 10 November is favourable with observations, including environmental compatibility. The proposal’s existence does not create any such exemption today. Official dossier; Legislative Council opinion.

What should readers watch next?

  • The L638 committee report, due on 16 November, and any amendments. The displayed first-chamber tacit-adoption date is 23 December; neither date guarantees final adoption or publication.
  • The separate progress of L597, L601 and B543. Provisions from different bills cannot be combined into an assumed new version of the Code.
  • OAR’s decision announced for December, which may replace the temporary professional procedure.

Cluj County Council’s proposals of 2 November provide context for difficulties reported by a local authority, including digital implementation and professional structures. They are an institutional position, not an instrument changing project requirements. Cluj County Council’s document and explanation.

Important information

This article provides general information and does not constitute legal advice or replace a qualified professional's assessment of your circumstances. Laws, official guidance, standards and product features can change. Check current primary sources and the requirements applicable to your jurisdiction, contract and project before making decisions. Examples illustrate the discussion; they are not official rulings or instructions for a particular case. For legal decisions, consult a qualified lawyer; for technical or other specialist matters, consult the responsible professional.

Enable JavaScript to use reading progress and usefulness ratings.