Annex 1 and Annex 2: what changes in practice

The central difference is who takes responsibility for Permanent Works design. The table describes the model’s defaults; read them together with the Agreement, permitted customisation and the version applicable to the project.

Example: the Annex 2 error notice

At the start of a school design, the team finds that the specified system flow does not match the user numbers in the Employer’s Requirements. It records the document and revision, describes the inconsistency and notifies the Supervisor within the contractual period, copying the Employer. It requests a Decision and identifies possible design and construction effects. If it seeks time or money, it separately submits the claim under 69a. Including an error in a report does not prove that it was undiscoverable before tender.

Read Annex 2 clauses 8.4–8.5 · Read Annex 1 clause 8.3

Practical examples

  • A school built to the Employer’s design (Annex 1). The Contractor finds that a foundation drawing leaves a connection unclear. It requests clarification and tracks the programme effect. If the solution must change, it follows design, checking, permit and contractual variation procedures; naming it an “execution detail” does not avoid those requirements.

  • A school designed and built by the Contractor (Annex 2). Its solution fails the mandatory energy performance in the Employer’s Requirements. Correcting its own design is, in principle, its responsibility. A new Employer requirement or an undiscoverable error in the Requirements is different: examine cls 8 and 37, notices and evidence.

  • Quantities: for a unit-price item at EUR 100/m³, 110 measured, compliant m³ means EUR 11,000 before adjustments and taxes even if the bill estimated 100 m³. For a EUR 10,000 lump-sum item, that extra consumption alone does not generate another EUR 1,000. These are fictional examples; a changed solution or an admissible claim requires separate assessment.

Annex 1 · official source · Annex 2 · official source

Important information

This guide provides general information, not legal advice or an assessment of your contract. The explanations and English translation are unofficial. Check the official Romanian text, applicable version and transitional rules for your procedure and project. Examples are not official rulings; consult a qualified lawyer for legal decisions and the responsible professional for technical matters.