HG 1/2018 · Legal text

Annex 1 · Works execution

General information — not legal advice. Romanian text reproduced from the official source; unofficial English translation.

About this edition and applicability

The Government Decision, General Conditions, Specific Conditions and Contract Agreement. Select the other annex or language in the top bar.

Source checked: 12 November 2026. Displayed consolidation: 24 May 2024. This version does not automatically apply to every older contract.

What the markings show

Gold highlighting identifies subclauses with official amendment notes, not individual inserted or deleted words. Blue notes explain related legislation and do not replace HG 1 wording. Switching off hides editorial markings; the consolidated text and official notes remain available.

Government Decision No 1/2018 · articles 1–5

Official Government Decision source

General Conditions

1Definitions

2Contract language

3Document precedence

4Communications

5Supervisor

6Assignment

7Subcontracting

8Employer documents

9Site access

10Permits and legal assistance

11Employer personnel

12General obligations

12aCode of conduct

12bConflicts of interest

13Management of the works

14Personnel

15Performance security

16Responsibilities and insurance

17Programme

18Price breakdown

19Design responsibilities

20Adequacy of the contract price

21Exceptional risks

22Site safety

23Adjacent property

24Traffic and access routes

25Utilities

26Setting out

27Site operations

28Discoveries

29Temporary works

30Plant and transport

31Overlapping contracts

32Intellectual property

33Commencement

34Time for completion

35Extension of time

36Delay

37Variations

38Suspension

39Site diary

40Materials and equipment

41Inspection and testing

42Rejection

43Ownership of materials

44Payment principles

45Contract value

46Advance payment

47Retention

48Price adjustment

49Valuation and payment schedule

50Interim payments

51Final payment

52Direct subcontractor payments

53Late payment

54Third-party payments

55Additional costs

56End of parties’ liability

57Acceptance principles

58Tests on completion

59Early use

60Taking over at completion

61Defects / warranty period

62Final acceptance

63Breach

64Termination by the Employer

65Termination by the Contractor

66Force majeure and unilateral termination

67Insolvency

68Risk allocation and indemnities

69Claims and decisions

69aContractor claims

69bEmployer claims

69cSupervisor decision

70Disputes and arbitration

71Governing law

72Control and audit

Specific Conditions and Contract Agreement

The General Conditions are presented clause by clause above. Below are the customisation rules and the Agreement form, separately, so you can find the project parameters quickly.

Official annex source

Important information

This guide provides general information, not legal advice or an assessment of your contract. The explanations and English translation are unofficial. Check the official Romanian text, applicable version and transitional rules for your procedure and project. Examples are not official rulings; consult a qualified lawyer for legal decisions and the responsible professional for technical matters.