General information — not legal advice.
Annex 1 and Annex 2: what changes in practice
The central difference is who takes responsibility for Permanent Works design. The table describes the model’s defaults; read them together with the Agreement, permitted customisation and the version applicable to the project.
| Topic | Annex 1 · Execution | Annex 2 · Design and build |
|---|---|---|
| Starting point · cl. 8 | The Employer supplies the technical design for execution. The Contractor organises delivery of the works defined by it. | The Employer’s Requirements define the outcome and mandatory characteristics. The Contractor develops the design; the feasibility study is supplied for information. |
| Who designs · cl. 19 | Execution does not exclude all design: the Contractor prepares Temporary Works, methodology and execution details that strictly implement the Employer’s design without changing it. | The Contractor designs Permanent and Temporary Works through qualified designers and fulfils the designer’s statutory duties. Supervisor approval does not transfer that responsibility. |
| Building permit · cls 10 and 19 | As a default, the Employer obtains the Permanent Works permit. The Contractor handles its other approvals, including Temporary Works; its own proposed variation can add duties. | The Contractor prepares the documentation and obtains associated approvals in the Employer’s name. The Employer obtains the permit; the default in 19.3(b) is 60 days after document approval unless the Agreement sets another period. |
| Early error review · 8.3 / 8.4–8.5 | There is no equivalent of Annex 2’s initial 90-day review procedure. Clause 8.3 requires notice of needed drawings or instructions, the required date and foreseeable delay. The absence of the 90-day procedure does not remove other notice duties. | Clause 8.4 requires scrutiny of the Employer’s Requirements and reference points, with errors notified within 90 days of the Start Date unless the Agreement sets another period. An “error report” can organise the notice; the model does not prescribe that title or automatically award extra time or money. |
| Which error supports a claim · 8.4–8.5, 69a | Check the document, responsibility and allocated risk; for missing drawings/instructions, 8.3 sets the conditions for relief. Retain the notice and evidence of the programme effect. | An error a diligent contractor could have discovered before tender does not justify extra time or value under 8.4. For errors not discoverable through the diligent review, 8.5 requires proven delay/cost and compliance with 69a. An error notice does not replace a claim notice. |
| A design error · cls 8, 19 and 37 | Identify the document’s author and the effect on the works. The Contractor notifies and requests instructions; a gap in the Employer’s design does not permit unilateral redesign. Its own methods and details remain its responsibility. | Errors in the Contractor’s design are corrected at its expense. For errors in the Employer’s Requirements, cls 8.4–8.5 examine what a diligent contractor could discover and notification within the contractual period. |
| Valuation for payment · cls 45 and 49 | Unit-price items are paid using actual measured quantities. Lump-sum items also exist. Extra quantity without changing drawings or specifications is not automatically a Variation (49.1). | The default is a lump-sum price, except Provisional Sums, subject to contractual adjustment and revision. Payments follow the Schedule of Payments; 45.4 requires Special Conditions for any parts paid by measurement. |
| Handover documents · cls 19 and 60 | For the construction technical record, the Contractor supplies chapter B (execution) documents and, where applicable, documents for A and D. Acceptance also requires the other contractual and statutory conditions. | The Contractor supplies chapters A (design) and B and, where applicable, D. Operation/maintenance manuals and training required before acceptance are separate conditions under 19.5. |
| What may be customised | The Agreement supplies project parameters. Specific Conditions permit Special Conditions for eight subclauses: 5.1, 8.1, 9.1, 9.2, 10.1, 19.2, 24.1, 44.1, only on the stated subjects. | The list has nine subclauses: 5.1, 8.2, 9.1, 9.2, 10.1, 19.2, 24.1, 44.1 and 45.4. Besides the different 8.2 reference, it includes measurement rules for identified parts. |
| Programme and approvals · 17, 19 | The programme coordinates execution, resources and Contractor documents. Track Employer drawings and required instructions against the dates needed for construction. | The programme includes design and its interfaces with approval, permitting, procurement and execution. Documents go to the Supervisor under 19.2; approval does not relieve the Contractor’s designer of responsibility. |
| Proposing a different solution · 37 | A new solution is not merely implementation of the Employer’s design. Technical review, approvals and the applicable contractual procedure are needed. | Clause 37.11 permits reasoned proposals at the Contractor’s cost but protects mandatory characteristics in the Employer’s Requirements, except errors handled under 8.4–8.5. A proposal is not approval. |
| Payment controls · 49.2, 50.3 | Measurement and applicable prices support certification. Supporting documents remain necessary; measuring non-compliant work does not itself make it payable. | The Supervisor compares scheduled payments with an alternative valuation of Permanent Works delivered, including documents. A significant difference may be temporarily withheld under 49.2; invoicing a milestone does not itself prove physical progress. |
| Security is not automatically split into design and construction | Works-contract security and its statutory/contractual release conditions apply. Retention Money and advance-payment security are distinct mechanisms. | Delivering the design does not automatically release a design share of the security. The integrated contract remains a works contract; rules for separately procured design services do not automatically transfer. |
Example: the Annex 2 error notice
At the start of a school design, the team finds that the specified system flow does not match the user numbers in the Employer’s Requirements. It records the document and revision, describes the inconsistency and notifies the Supervisor within the contractual period, copying the Employer. It requests a Decision and identifies possible design and construction effects. If it seeks time or money, it separately submits the claim under 69a. Including an error in a report does not prove that it was undiscoverable before tender.
Read Annex 2 clauses 8.4–8.5 · Read Annex 1 clause 8.3
Practical examples
A school built to the Employer’s design (Annex 1). The Contractor finds that a foundation drawing leaves a connection unclear. It requests clarification and tracks the programme effect. If the solution must change, it follows design, checking, permit and contractual variation procedures; naming it an “execution detail” does not avoid those requirements.
A school designed and built by the Contractor (Annex 2). Its solution fails the mandatory energy performance in the Employer’s Requirements. Correcting its own design is, in principle, its responsibility. A new Employer requirement or an undiscoverable error in the Requirements is different: examine cls 8 and 37, notices and evidence.
Quantities: for a unit-price item at EUR 100/m³, 110 measured, compliant m³ means EUR 11,000 before adjustments and taxes even if the bill estimated 100 m³. For a EUR 10,000 lump-sum item, that extra consumption alone does not generate another EUR 1,000. These are fictional examples; a changed solution or an admissible claim requires separate assessment.
Important information
This guide provides general information, not legal advice or an assessment of your contract. The explanations and English translation are unofficial. Check the official Romanian text, applicable version and transitional rules for your procedure and project. Examples are not official rulings; consult a qualified lawyer for legal decisions and the responsible professional for technical matters.